(06-04-2015, 10:23 AM)Canard Wrote: Faster? Weber St. seemed like it went really, really fast, given the scope of work involved. I imagine King would take a little longer. Although for King, they won't have to make a bypass road like they did for Weber.
Weber st did seem really fast, but like you said, with no bypass road, should it not take less time?
Posts: 2,163
Threads: 17
Joined: Sep 2014
Reputation:
77
I believe the King St overpass is a longer span. The maximum length they can build without a central support.
The main reason for the lack of a bypass road, is that the site is quite constrained on two corners. They can't conveniently knock down the Breithaupt Block or School of Pharmacy to build a bypass. In the case of Weber, the bypass road construction/destruction only looked to add a month or so to the schedule. Efforts for it were largely parallelizable with the underpass work itself.
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
06-04-2015, 11:34 AM
(This post was last modified: 06-04-2015, 11:34 AM by Canard.)
Latest ion update also mentions the ramps to/from 85 at Northfield will be closed for 18 months as well starting on June 8 - wow! I didn't think any work was starting on Northfield until next year.
Posts: 1,095
Threads: 2
Joined: Aug 2014
Reputation:
33
Perhaps they moved it up to take place of the work Uptown?
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
I can't imagine that would be quick to do, from a project management standpoint. Scheduling of equipment, resources, etc.
Posts: 289
Threads: 27
Joined: Sep 2014
Reputation:
5
If I can recall too, the grade separation of Hespeler Road over the tracks at the Delta intersection went fairly quickly.
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
06-04-2015, 06:14 PM
(This post was last modified: 06-04-2015, 06:57 PM by Canard.)
Bearanger is back open to traffic now.
Substation work at Clay and Glass:
Alignment between Bearanger and McCormic Arena:
Completed crossing at Bearanger:
Temporary Old/New rail fish plate interface:
Current end of the line for the new track:
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
Posts: 1,935
Threads: 102
Joined: Aug 2014
Reputation:
18
Canard great pictures, I was going to post some similar ones that I took yesterday of the maintenance building but yours sums up the situation well.
I noticed that the OMSF site has preparations complete for a couple of additional buildings or structures
Posts: 776
Threads: 2
Joined: Oct 2014
Reputation:
44
Canard : I thought the substation was going to be located closer to the pedestrian/rail bridges closer to waterloo park? Did they move it?
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
There's a second pad there as well. I tried to get a photo, but it didn't turn out very well.
Posts: 4,589
Threads: 16
Joined: Aug 2014
Reputation:
147
A lot of heavy work in the rail corridor between Ottawa and the expressway over the last couple days - a lot of grading makes for a clear open vista.
Posts: 776
Threads: 2
Joined: Oct 2014
Reputation:
44
(06-05-2015, 05:35 AM)Canard Wrote: There's a second pad there as well. I tried to get a photo, but it didn't turn out very well.
Thank you.
Posts: 4,475
Threads: 1
Joined: May 2015
Reputation:
208
(06-05-2015, 05:35 AM)Canard Wrote: There's a second pad there as well. I tried to get a photo, but it didn't turn out very well.
Last I heard, the substation will now be just on the other side of the Laurel Creek crossing. In recent days I have seen a space being graded, presumably for the substation. I expect it will eventually almost disappear into the forest. This is a change from the location beside Father David Bauer Dr.
I believe the concrete pad beside CCGG is the top of the Laurel Creek structure. Apparently it requires reinforcing, which explains the work done. I’m unclear on why reinforcement is necessary, since heavy rail has been crossing it for decades. Maybe it is getting worn out. The Laurel Creek structure is also currently exposed crossing Caroline St. where, in addition to the reinforcements that I believe are also needed there, significant changes to the way the storm sewer works are also being made.
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
Hmm, the pad next to Clay and Glass was newly-poured concrete, and had services sticking out of it... Didn't look like it was related to the little water tunnel. Could be wrong of course, and it is on a strange angle relative to the track alignment. You'd think if it was substation or track related, it'd be parallel to the tracks.
|