Posts: 4,340
Threads: 1
Joined: May 2015
Reputation:
180
Does anybody know how FIE installation is going? The last I was aware, all 14 LRVs were on site, with FIE installed in about 7 of them and presumably work continuing on completing the installation in the remaining vehicles.
Posts: 7,603
Threads: 36
Joined: Jun 2016
Reputation:
197
(01-18-2019, 01:35 PM)Canard Wrote: That actually sounds entirely plausible!
To be honest, I’m amazed we’ve had nearly a year of (very limited) operations under our belt without a single LRV-Pedestrian or LRV-Automobile conflict yet. Houston had 70+ Accidents the first year.
I'm not, between limited operations and *extremely* cautious operators (coming to a near complete stop at some corners, when facing a green), they're clearly trying to minimize risk. Also see the plausible suggestion they're avoiding rush hour.
Which bugs me a little bit, when this is operating, it will operate during rush hour. There are serious problems that need to be rectified before it can operate smoothly (the turn off King in uptown is blocked by cars about 70% of the time I go past). We've been testing long enough, if we're not comfortable operating in rush hour yet, it just makes me more anxious about timelines.
Posts: 671
Threads: 2
Joined: Oct 2014
Reputation:
24
(01-18-2019, 02:01 PM)ijmorlan Wrote: Does anybody know how FIE installation is going? The last I was aware, all 14 LRVs were on site, with FIE installed in about 7 of them and presumably work continuing on completing the installation in the remaining vehicles.
The last report on CTV Kitchener news on around the first week of January stated that all 14 vehicles had the FIE installed! by the end of 2018 (as promised)
Posts: 4,913
Threads: 155
Joined: Aug 2014
Reputation:
119
(01-18-2019, 01:35 PM)Canard Wrote: That actually sounds entirely plausible!
To be honest, I’m amazed we’ve had nearly a year of (very limited) operations under our belt without a single LRV-Pedestrian or LRV-Automobile conflict yet. Houston had 70+ Accidents the first year.
70?!?! Wow!
I'm glad things have gone smoothly. No ammo for the anti-LRT folk out there
Posts: 838
Threads: 10
Joined: Jul 2017
Reputation:
45
Regarding rush hour, I see a train almost every day at Charles and Stirling at around 8:20, and another pulling into Victoria Park station around 8:30. It's not the worse part of rush, but Charles between Water and Gaukel starts building up with Manulife employees pulling into the garages. Relatedly, I'm pretty impressed by the regularity of it. I wonder if they're running a schedule right now? My guess is they must have to to get the 600 hour burn-in done appropriately, although the trains are almost always empty but for 3-5 GRT staff clustered in the cab.
Posts: 667
Threads: 0
Joined: Feb 2017
Reputation:
26
01-18-2019, 03:55 PM
(This post was last modified: 01-18-2019, 03:56 PM by trainspotter139.)
Posts: 810
Threads: 5
Joined: Nov 2015
Reputation:
39
01-18-2019, 06:37 PM
(This post was last modified: 01-18-2019, 06:37 PM by Bob_McBob.)
A couple weeks ago CTV reported none of the LRVs had received preliminary acceptance certification yet, so they couldn't have been doing any burn-in as of then. Plus I'm sure the radio listeners here would be the first to report on any discussion of burn-in.
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
All I ever heard is training of operators, in the evenings and on weekends, but apparently mid-day there's talk of FIE integration testing as of this week.
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
Some kind of protest is happening between Grand River Hospital Central Station, so it is causing some problems today for Testing + Training. The police have parked on the tracks.
Posts: 6,491
Threads: 38
Joined: Aug 2014
Reputation:
88
01-19-2019, 11:36 AM
(This post was last modified: 01-19-2019, 11:36 AM by panamaniac.)
Related to the news yesterday of layoffs coming at GRH, perhaps.
Posts: 7,603
Threads: 36
Joined: Jun 2016
Reputation:
197
Sounds like it was the KW women's March.
Posts: 89
Threads: 1
Joined: Jun 2018
Reputation:
8
(01-19-2019, 11:26 AM)Canard Wrote: Some kind of protest is happening between Grand River Hospital Central Station, so it is causing some problems today for Testing + Training. The police have parked on the tracks.
doesn't seem like that's stopping them, sounds like 507 and 511 are out the whole length of the line today
Posts: 4,340
Threads: 1
Joined: May 2015
Reputation:
180
This thread just shrank from 911 to 906 pages. Anybody know what happened?
It’s probably the record holder either way, just curious…
Posts: 581
Threads: 2
Joined: Oct 2017
Reputation:
26
(01-19-2019, 01:16 PM)ijmorlan Wrote: This thread just shrank from 911 to 906 pages. Anybody know what happened?
It’s probably the record holder either way, just curious…
I'm showing 904
edit: This post made it 905
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
|