09-19-2018, 12:49 PM
Please wait until Monday to arrive.
|
ION - Waterloo Region's Light Rail Transit
|
|
09-19-2018, 12:49 PM
Please wait until Monday to arrive.
09-19-2018, 02:05 PM
I looked closely at the ION train at the University of Waterloo today. It's #506. They have a bunch of computer screens in the dash but there is still an open slot for a screen. So I guess we're still waiting on those. (Will upload pictures in a bit). The testing cadence seems to have recently increased. Hope the Council report has good news.
09-19-2018, 02:20 PM
The “hole” is where the specialized equipment (“FIE” or Free-Issued Equipment) is to be installed. The vehicle en-route from Millhaven (511) is the first one equipped with it. Three more vehicles here have begun some of the preliminary installation steps, from what I understand.
Earlier this afternoon, crews were using an LRV on King in Midtown (between Kitchener and Waterloo) doing sound testing. Police would block off a ~500 m section, allow the cars to filter away, then the LRV would go past big elaborate microphone stands on either side of the road. Pretty neat!
Any sign of that PDF LRV update yet? Tom said it's on the Region's site... but made no reference to where.
09-19-2018, 03:28 PM
(This post was last modified: 09-19-2018, 03:29 PM by trainspotter139.)
(09-19-2018, 03:20 PM)Canard Wrote: Earlier this afternoon, crews were using an LRV on King in Midtown (between Kitchener and Waterloo) doing sound testing. Police would block off a ~500 m section, allow the cars to filter away, then the LRV would go past big elaborate microphone stands on either side of the road. Pretty neat! https://calendar.regionofwaterloo.ca/Cou...df#page=13 Embedded at the end of the revised agenda for the council meeting today
09-19-2018, 06:08 PM
(This post was last modified: 09-19-2018, 10:13 PM by Pheidippides.)
Can someone explain this sentence?:
"To expedite installation one train (Vehicle 510) will remain in Kingston for on-board installations, rather than complete installations in Waterloo as originally planned." I thought 510 was always going to stay in Kingston for on-board installations; how is this different? The document says installation is half-way done on 502/503/504 after starting on July 16. Installation is "expected to be complete in late September/early October." July 16 to October 1 is 77 days (54 work days). 54 workdays from October 1 is December 18. That's cutting it pretty close (and that's not including at testing of the newly installed equipment). Even if they halve the time for the next 5 Waterloo installations, which seems unlikely given that there would be 5 not the current 3 they are working on, that would be 27 days or November 8 - still not a lot of wiggle room.
Everyone move to the back of the bus and we all get home faster.
09-19-2018, 06:33 PM
(09-19-2018, 06:08 PM)Pheidippides Wrote: The document says installation is half-way done on 502/504/504 after starting on July 16. Installation is "expected to be complete in late September/early October." Why October? The document was published today. The 51% progress update is surely from some time earlier. If we assume it's from last Friday, for example, it's 43 work days. Add another 43 days to last Friday and we get 16 November 2018.
09-19-2018, 06:40 PM
(This post was last modified: 09-19-2018, 10:13 PM by Pheidippides.)
(09-19-2018, 06:33 PM)tomh009 Wrote:(09-19-2018, 06:08 PM)Pheidippides Wrote: The document says installation is half-way done on 502/503/504 after starting on July 16. Installation is "expected to be complete in late September/early October." We don't need to know the date 51% completion was achieved. From the report we know the start date (July 16) and an expected end date (late September/early October) which allows us to calculate the duration of the procedure.
Everyone move to the back of the bus and we all get home faster.
09-19-2018, 07:20 PM
It's also worth noting that work should proceed more quickly on subsequent vehicles. No matter how well defined a process, there is always a learning curve that won't be repeated with subsequent installations.
09-19-2018, 07:40 PM
09-19-2018, 07:50 PM
Don't worry, 515 will have the super duper special equipment to start the learning curve again.
09-19-2018, 08:37 PM
1/1 - Saturday, September 15, 2018
King St. Grade Separation Tour - Doors Open Waterloo, 2018
09-19-2018, 08:38 PM
1/1 - Wednesday, September 19, 2018
The grin says it all. Oh, the stories this hole could tell...
09-19-2018, 08:47 PM
I was hoping we'd get one of your big photo updates soon. Thanks Canard!!
Love the look of these inside.
First fully equipped Ion train on its way to region
"Galloway said the service is still on track to launch in December. However, there's "no wiggle room for any major or significant delays."" |
|
« Next Oldest | Next Newest »
|