In order to take advantage of all the great features that Waterloo Region Connected has to offer, including participating in the lively discussions below, you're going to have to register. The good news is that it'll take less than a minute and you can get started enjoying Waterloo Region's best online community right away.
or Create an Account




Thread Rating:
  • 16 Vote(s) - 4 Average
  • 1
  • 2
  • 3
  • 4
  • 5
ION - Waterloo Region's Light Rail Transit
$1500/day/vehicle, to a maximum of $3.3M.

(First vehicle is now early Feb BTW. Ugh)
Reply


So based on that schedule: 14 vehicles x 10 months x 30 days/mo x $1500/day  = 6M+ 

That's taking some liberties (with my math) but really starting to add up.
Reply
But it's capped at $3.3M.
Reply
So once you know that you're paying $3.3 million whether you deliver really quickly or really slowly, the latter option seems especially compelling.
Reply
Exactly. This is what Toronto was into several months ago with the streetcar (FLEXITY Outlook) order.

"We're gonna sue you for our full $52 million Penalty clause!"

"..ok"

"..but still hurry!"

"...no?"
Reply
(12-13-2016, 02:18 PM)Pheidippides Wrote: Sadly we have just passed what was supposed to have been a major milestone. According to a May 2016 report that seems to reference the original "agreement" trains 2 to 14 were supposed to have been here 10-Dec-2016 which means late fees are now being applied to all 14 trains now. I think it was about a week after this report that news of the revised schedule broke setting the completion date for all 14 back 10 months to October of 2017.
 
http://www.regionofwaterloo.ca/en/region...pdf#page=3
 
On August 20, 2013 the Region entered into an Agreement with Bombardier Transportation Canada Inc. (“Bombardier”) for the purchase of 14 Light Rail Vehicles in connection with the Light Rail Transit Project (the “Agreement. The Agreement includes delivery of the first light rail vehicle by “no earlier than May 1, 2016 and no later than August 15, 2016” and delivery of the second to fourteenth vehicle by December 10, 2016.

Are being applied, or could be applied?
Reply
(12-13-2016, 04:56 PM)Viewfromthe42 Wrote: So once you know that you're paying $3.3 million whether you deliver really quickly or really slowly, the latter option seems especially compelling.

Hence my question, above.
Reply


Decision hasn't been made yet.
Reply
(12-13-2016, 05:15 PM)Canard Wrote: Decision hasn't been made yet.

And I imagine won't be for some time, for the obvious reason.
Reply
Yeah. If Bombardier knows if they try hard enough, we won't exercise the penalty clause, then that's good for everyone. We get our trains a little late, but relations stay warm and fuzzy.

If they know no matter what were going to use the full $3.3M penalty clause, then there's no incentive to hit any deadline at all. They know there's no way we'll cancel the order and delay opening 3-5 years by re-tendering.
Reply
Does a possibility exist for further legal action beyond the penalties in the contract?
Reply
Not really, no.

As Tom Galloway'a said, we want trains, not discounts.
Reply
(12-13-2016, 06:16 PM)timc Wrote: Does a possibility exist for further legal action beyond the penalties in the contract?

Yes, really yes.

Or at least that's what the record wrote a few weeks back:

http://www.therecord.com/news-story/6981...2-million/

"The full financial implications of the delays are not yet certain. The region will pursue options to recover costs associated with the delay from Bombardier. In the contract, the provision for late trains is $1,500 per day, per train, up to a maximum of $3.3 million. The region can also seek further damages."
Reply


(12-13-2016, 02:18 PM)Pheidippides Wrote: Sadly we have just passed what was supposed to have been a major milestone. According to a May 2016 report that seems to reference the original "agreement" trains 2 to 14 were supposed to have been here 10-Dec-2016 which means late fees are now being applied to all 14 trains now. I think it was about a week after this report that news of the revised schedule broke setting the completion date for all 14 back 10 months to October of 2017.
 
http://www.regionofwaterloo.ca/en/region...pdf#page=3
 
On August 20, 2013 the Region entered into an Agreement with Bombardier Transportation Canada Inc. (“Bombardier”) for the purchase of 14 Light Rail Vehicles in connection with the Light Rail Transit Project (the “Agreement. The Agreement includes delivery of the first light rail vehicle by “no earlier than May 1, 2016 and no later than August 15, 2016” and delivery of the second to fourteenth vehicle by December 10, 2016.

Of course we wouldn't have been ready to receive 14 train sets last week anyway ... or the first train set in August.  Our track construction is also behind schedule, although not as much as Bombardier.
Reply
(12-13-2016, 07:04 PM)tomh009 Wrote: Of course we wouldn't have been ready to receive 14 train sets last week anyway ... or the first train set in August.  Our track construction is also behind schedule, although not as much as Bombardier.

The storage tracks at the maintenance facility looked pretty good at the Open House. I'm sure they would have been able to park them no problem.
Not to mention, if there was actual sign of receiving vehicles, I imagine that certain parts of the maintenance facility would have been higher up on the construction schedule. As it stands, there was no rush.
Reply
« Next Oldest | Next Newest »



Forum Jump:


Users browsing this thread: 13 Guest(s)

About Waterloo Region Connected

Launched in August 2014, Waterloo Region Connected is an online community that brings together all the things that make Waterloo Region great. Waterloo Region Connected provides user-driven content fueled by a lively discussion forum covering topics like urban development, transportation projects, heritage issues, businesses and other issues of interest to those in Kitchener, Waterloo, Cambridge and the four Townships - North Dumfries, Wellesley, Wilmot, and Woolwich.

              User Links