07-22-2016, 12:49 PM
Will let you know in a few hours!
|
ION - Waterloo Region's Light Rail Transit
|
|
07-22-2016, 12:49 PM
Will let you know in a few hours!
07-22-2016, 01:28 PM
Track is now embedded from Water/Duke to Duke/Beer Store.
07-22-2016, 01:32 PM
You mean Francis, right?
07-22-2016, 02:06 PM
It would involve both Duke and Francis, I believe.
07-22-2016, 02:08 PM
Beer store is on Francis
07-22-2016, 02:55 PM
Yes, to Francis/Beer Store, that is what I meant. The curve that goes through Francis/King is not complete.
07-22-2016, 05:05 PM
Construction update is out. I see the intersection of Duke and King is closing next week... again. I'd like to visit this mythical intersection and see what's being done.
07-22-2016, 05:09 PM
(07-22-2016, 05:05 PM)timio Wrote: Construction update is out. I see the intersection of Duke and King is closing next week... again. I'd like to visit this mythical intersection and see what's being done. Wow sure enough: http://us8.campaign-archive1.com/?u=a082...9b00cab7&e= Quote:Frederick/Benton, Charles to Weber, in Kitchener
07-22-2016, 05:18 PM
Clearly that should say King/Frederick.
07-22-2016, 05:50 PM
07-22-2016, 06:10 PM
Couldn't see Ottawa/Charles but I doubt it's open.
Just drove down Courtland; 2-way now between Block Line and Manitou! Charles is now open 2-way between Borden and Stirling! Bit by bit, more things are opening than are closing. Home stretch! Quote:Just drove down Courtland; 2-way now between Block Line and Manitou! I'm very happy to read this!
07-22-2016, 08:41 PM
07-22-2016, 09:16 PM
The update suggests it will be granular when it opens.
07-22-2016, 09:16 PM
(07-22-2016, 08:41 PM)Markster Wrote:(07-22-2016, 06:10 PM)Canard Wrote: Couldn't see Ottawa/Charles but I doubt it's open. Seems that it will reopen, but not be complete (much like Duke / College and Duke / Young at the moment). Night work is being preformed next week on the CN track near Borden. They'll be shifting those over to build the incline for the Ion tracks, I'll bet. Also: Quote: Why's that? What around-the-clock working is necessary for that stretch, being that it's basically complete apart from signals being reactivated? I don't suppose it's for taking dow the hydro poles, is it? |
|