According to the Council agenda for this week:
- The Region has cancelled the contract for bus stop snow clearing in Kitchener and has tendered a snow clearing contract with one of the companies clearing stops in other parts of the Region.
- The University of Waterloo Station project is being scaled back initially as bids exceeded the budget for the project
- The installation of the preferred canopies for transit riders is being delayed until a later date to reduce the cost of the contract.
- They will use the shelters from decommissioned terminals temporarily in place of the preferred canopies.
- The plan is to have the terminal completed by Fall 2019.