03-03-2017, 10:10 PM
Some Ion related items under budget, some over:
http://calendar.regionofwaterloo.ca/Coun...df#page=66
I like how the name of this project (which I am guessing is the construction dome):
05441 RR15(King)GEXR Crossing‐Subway Installation
$1,844,000 over budget
"Actual costs are under review with the contractor and will be finalized in 2017"
05041 RR15(King)Victoria St RR55
$478,000 under budget
"LRT related project, works are not yet completed. Will be completed in 2017"
06206 RR15 King Central Mkt to Union
$162,000 over budget
"This is an RT project and was not completed during 2016 ‐ Project will be carried forward into 2017"
ION project
$4,198,000 under budget
"Project spending is ongoing, overall variance is 1.5%"
http://calendar.regionofwaterloo.ca/Coun...df#page=66
I like how the name of this project (which I am guessing is the construction dome):
05441 RR15(King)GEXR Crossing‐Subway Installation
$1,844,000 over budget
"Actual costs are under review with the contractor and will be finalized in 2017"
05041 RR15(King)Victoria St RR55
$478,000 under budget
"LRT related project, works are not yet completed. Will be completed in 2017"
06206 RR15 King Central Mkt to Union
$162,000 over budget
"This is an RT project and was not completed during 2016 ‐ Project will be carried forward into 2017"
ION project
$4,198,000 under budget
"Project spending is ongoing, overall variance is 1.5%"
Everyone move to the back of the bus and we all get home faster.