04-26-2016, 10:26 AM
(04-26-2016, 09:52 AM)zanate Wrote:(04-26-2016, 09:41 AM)KW65 Wrote: Yes, but the LRT train tunnel under the expressway - paid by the LRT project- extended the construction by one year. This was not part of the 2011 time line estimates for finishing the project.
Good info, I should afford some benefit of the doubt for that. Out of curiosity, do you have any reference information that the time delay was attributed to the tunnel?
This is a ROW memorandum of the existing contract "Change Order" to construct the new LRT tunnel for $11 million , dated July 2013 and agreed upon by the MTO and Dufferin Construction. Note that this was well after the highway construction had started. Also of note, Grandlinq's expenditure page says this part of the project cost $11.2 million.
https://rapidtransit.regionofwaterloo.ca...uction.pdf