(04-25-2016, 07:04 PM)panamaniac Wrote: Isn't the work on schedule?
I believe it was scheduled from 2011 - 2016 with minor work at the start and finish. That's why the Homer Watson / Ottawa and Alpine / Ottawa roundabouts were originally supposed to start this year (have since been postponed until after the LRT is done to limit major detours in every part of town).
2011: Startup work
2012: Fischer Hallman - Homer Watson (Fischer Hallman on-ramp and Westmount overpass)
2013: Courtland - Ottawa (Courtland and LRT overpass - one direction)
2014: Courtland - Ottawa (Courtland and LRT overpass - other direction)
2015: Ottawa - Homer Watson (Ottawa and Homer Watson overpasses)
2016: Finishing touches