You're welcome!
The critical pour is the deck on top, which is a staggering two metres thick. The temperature must be at 10C for at least a week for the concrete to properly set.
The critical pour is the deck on top, which is a staggering two metres thick. The temperature must be at 10C for at least a week for the concrete to properly set.