Benton was complete today! All that's left to do is reactivate the traffic lights and move the barriers. Looks phenomenal. The first big intersection down!
![[Image: BcofFN8.jpg]](http://i.imgur.com/BcofFN8.jpg)
![[Image: EEXep9U.jpg]](http://i.imgur.com/EEXep9U.jpg)
Looking down Charles. You can see they're prepping the NB curbs down to Eby.Didn't actually go to Eby, so I'm not sure if they go farther, but I doubt it; Cedar is still torn up. The Cedar station has started to become framed though!
![[Image: EAI86T2.jpg]](http://i.imgur.com/EAI86T2.jpg)
Pandora / Charles is torn up as well. I think they're adjusting the slope here, now that the retaining wall is done.
All curbs are officially in on Charles between Stirling / Borden. The first directionally-divided road to have all it's curbs finished.
On King: large metal hydro poles (like the ones they replaced with in front of GRH) are lying down from Wellington onwards. I guess they'll be doing those too?
The front entrance to KCI has been completely graded down now. They'll start the stairs soon, I assume.
They've started boring holes for cat poles in front of GRH.
I forgot to pay attention: when turning right from Union E onto King S, is there still that separate turning segment? Or is that gone, and it's a standard 4 way intersection now? I'd like to update Google Maps to reflect.
![[Image: BcofFN8.jpg]](http://i.imgur.com/BcofFN8.jpg)
![[Image: EEXep9U.jpg]](http://i.imgur.com/EEXep9U.jpg)
Looking down Charles. You can see they're prepping the NB curbs down to Eby.Didn't actually go to Eby, so I'm not sure if they go farther, but I doubt it; Cedar is still torn up. The Cedar station has started to become framed though!
![[Image: EAI86T2.jpg]](http://i.imgur.com/EAI86T2.jpg)
Pandora / Charles is torn up as well. I think they're adjusting the slope here, now that the retaining wall is done.
All curbs are officially in on Charles between Stirling / Borden. The first directionally-divided road to have all it's curbs finished.
On King: large metal hydro poles (like the ones they replaced with in front of GRH) are lying down from Wellington onwards. I guess they'll be doing those too?
The front entrance to KCI has been completely graded down now. They'll start the stairs soon, I assume.
They've started boring holes for cat poles in front of GRH.
I forgot to pay attention: when turning right from Union E onto King S, is there still that separate turning segment? Or is that gone, and it's a standard 4 way intersection now? I'd like to update Google Maps to reflect.