(06-08-2026, 04:47 PM)taylortbb Wrote: GO will be doing consultations June 22 & 24 for track expansion between Georgetown and Bramlea, https://www.metrolinx.com/en/projects-an...-june-2026 . This work is the main blocker for two-way all-day GO to KW, so hopefully we'll finally get some details about what exactly they're going to build and what the timelines are.
Well for those who want the sneak peak peek here you go.
It'll be triple track from Georgetown to the far side of the Credit River Bridge, at which point it'll go right to quad track, then at 10th line the two north tracks (GO) curve off the existing right of way to then pass under the two CN tracks and then curve back to the existing right of way, at which point CN is the northern most tracks and GO is the southern. Then it'll be quad track from there (Winston Churchill) to Downtown Brampton where it narrows back to triple track, before widening back to quad on the Bramlea side of Brampton.
The scope of work is pretty immense but it includes a substantial amount of realigned and new storm sewer, and a significant amount of bridge and retaining wall works.
Things may have been refined since I last saw the plans but they were at 60% design for most of the corridor at that point and things don't change much from 60 to 90 to 100.