(04-16-2026, 09:21 PM)ZEBuilder Wrote: They have way more than a rough idea of the bridge design, they're past the 90% design stage and know exactly where piers are going along with dozens of other aspects, they have a few outstanding issues to work through and then the bridge design is complete but those issues won't substantially change the design. In general when it comes to design work there are minimal changes between 90% and 100%, 60% and 90% are often very similar as well so they could have started grading works at 60% and have minimal rework when it comes time to actual construction.
That makes sense. Thanks.
I saw one weird summary of a contract (tender?) that seemed to say completion was in 2029. Do you know if that is the whole bridge or just the design or something in between or just some nonsense I misinterpreted?