In order to take advantage of all the great features that Waterloo Region Connected has to offer, including participating in the lively discussions below, you're going to have to register. The good news is that it'll take less than a minute and you can get started enjoying Waterloo Region's best online community right away.
or Create an Account




Thread Rating:
  • 2 Vote(s) - 4.5 Average
  • 1
  • 2
  • 3
  • 4
  • 5
ION Phase 2 - Cambridge's Light Rail Transit
(05-27-2023, 06:12 PM)ac3r Wrote:
(05-27-2023, 05:26 PM)Bytor Wrote: That's not something that you can say with certainty.

First, something that came out of the Council discussoons on Stage 2 ION on Wednesday was that Stage 1 had an initial budget of $818M and $12M or 1.5% was contingency., so $806M. The Problems with Bombardier and disagreements with GrandLinq on some things added $50M to the budget, bring it up to $868M, or $806M + $62M contingency. That's 7.7% contingency or over budget, whichever way you want to put it.

Second, what also came out of that Wednesday meeting was that the cost estimation was done with only an accuracy of -25% to +50%, a very wide range, and that the numbers publicised re cost were that maximum +50% number. The further you get from the centre of that estimate the less likely the estimate is.

That means the real likely cost is not $2.72B in 2022$, but rather $272B / 150% = $1.81B, far closer to and much more in line with the previous estimates of $1.4B to $1.6B from a handful of years ago.

Further, that means that the $1B of estimated inflation to 2033, which was assumed to be ~3.2%, is really only $670M for a total of $2.48B.

In turn, that means the 20% contingency is not $744M, but really only $496M, bring it to $2.98B in 2033$, not $4.76B.

But, since we now know what do to, what not to do, and how to do it, lesson learned and all that, and we need less than 8% contingency last time, do we really need and would we even use a 20% contingency? 10% woudl bring it down to $2.72B in 2033 dollars.

So why is the Council only harping that top unlikely cost of $4.76B? It's almost like they are deliberately trying to kill the project by doing that.

This is absolute nonsense. The Region of Waterloo did not just inflate numbers to "kill the project". Do you really think this is how things work? Lol.

I don't know what kind of education or career background you have in regards to massive building and infrastructure projects (if any), but I can tell you're just making stuff up here for some reason.

This price could potentially be reduced but it isn't going to be (not by much, anyway). This project may or may not go ahead (hopefully not) but if it does indeed, the invoice is going to be about what they're already asking for.

You're ignoring that the they literally sayings in council that estimate was not a very precise one and had a very wide range, -25% to +50% wrong.
Reply
« Next Oldest | Next Newest »



Messages In This Thread
RE: ION Phase 2 - Cambridge's Light Rail Transit - by Bytor - 05-27-2023, 08:10 PM

Forum Jump:


Users browsing this thread: 44 Guest(s)

About Waterloo Region Connected

Launched in August 2014, Waterloo Region Connected is an online community that brings together all the things that make Waterloo Region great. Waterloo Region Connected provides user-driven content fueled by a lively discussion forum covering topics like urban development, transportation projects, heritage issues, businesses and other issues of interest to those in Kitchener, Waterloo, Cambridge and the four Townships - North Dumfries, Wellesley, Wilmot, and Woolwich.