02-20-2023, 12:36 PM
(02-20-2023, 12:26 PM)cherrypark Wrote:(02-19-2023, 10:15 PM)dtkvictim Wrote: Checked out Joseph St and Stewart St today, and utility poles have still not been moved. The trail portion next to the Google parking garage looks finished. Found an update on EngageWR saying construction won't resume until summer 2023; a completely ridiculous timeline for this project.
Complete guess but the latter point sounds like the construction around the new incubator is going to encroach on the new MUT. Itching to have it done as well but if it saves the newly paved infra from getting busted up by construction I think its liveable. Not sure why Stewart St. couldn't get done in the mean time though...
AFAIK the project is actually the responsibility of the incubator developer.