08-16-2015, 11:17 PM
(08-16-2015, 09:51 PM)GtwoK Wrote: I'm curious now; when they have all the "utility work" (ie water mains, sanitary, storm) to do on the roads that the track will be running along, what is it they're actually DOING? I had hypothesized that they would want no interruption to to Ion service at any point, and therefore no construction involving track removal. As such, they were probably replacing water mains et al to something permanent, that would't require ever being replaced.
My understanding/guess is that it is a combination of moving the utilities so they are not under the tracks, and setting up the utilities in such a way that they can be serviced from the side (in particular, at intersections).