08-13-2020, 04:09 PM
No. My best guess is that they have paused the precast installation while they do the brickwork, so as not to crane massive precast slabs over the heads of the bricklayers.
The Bow (Arrow phase II) | 15 fl | Completed
|
08-13-2020, 04:09 PM
No. My best guess is that they have paused the precast installation while they do the brickwork, so as not to crane massive precast slabs over the heads of the bricklayers.
08-13-2020, 04:16 PM
That the Barra Castle lofts in the background?
08-13-2020, 06:04 PM
Yes, it is.
08-14-2020, 10:53 AM
Benton St facade brickwork under way.
08-14-2020, 10:58 AM
08-14-2020, 11:05 AM
Sometimes Tom forgets what street he lives on ....
08-14-2020, 11:47 AM
Duh, Charles on the brain! Benton it is. Fixing it now!
08-17-2020, 04:12 PM
Word from Auburn is the crane is broken, which I assume accounts for the delay in adding more floors.
08-17-2020, 09:19 PM
08-18-2020, 08:02 AM
I saw massive mobile crane driving into town this morning, maybe they are headed there to fix the crane..
08-18-2020, 10:35 AM
08-18-2020, 08:43 PM
08-21-2020, 08:33 PM
08-21-2020, 08:57 PM
Who obsorbs this cost ? The crane rental company ? And who has to pay for construction delays ?