01-24-2023, 08:25 AM
Should we place bets on when this pops above grade?
TEK Tower (30 Francis) | 45 fl | U/C
|
01-24-2023, 08:25 AM
Should we place bets on when this pops above grade?
01-24-2023, 08:58 AM
October...
01-25-2023, 10:16 AM
They are going hammer and tongs on this thing. Cement pump truck onsite again today, crane is dropping more supplies. They might break ground late spring/early summer at this pace.
01-25-2023, 07:35 PM
Agreed they are moving fast. They were pouring concrete on the same day as removing the last of that fill. Here they are tying rebar last Saturday.
I don't know the normal timeline to break ground, but bet they'll beat it. https://imgur.com/a/FGrSNh8
Digging a hole is easy. The piles, concrete mat, anchors, walls and then the initial infrastructure (waterproofing, drainage, pipes & utility connections, wires and electrical junctions) and so on take a lot longer. It'll be a while until it goes above grade.
They're closing off the street for 5 years which is roughly average for a 44 floor skyscraper. It won't mean it will all be closed off that entire time, but it'll still take a while for this thing. Charlie West started in early-mid 2018 and it only just finished up recently (including fully opening Gaukel Street).
01-25-2023, 09:15 PM
The permit to build hasn’t been issued yet. Only the permit for the foundation and underslab work. Although it’s been pended for a long time now
https://onlinepermits.kitchener.ca/portal/sfjsp
01-25-2023, 09:43 PM
You can consider this approved though haha. Like 900 King West which was excavated down to about 1 floor...then formally "approved" a few months later. I think Elevate Condos had the same course. The ball is usually rolling over Sisyphus before it gets rolled back up for formal approval.
01-25-2023, 10:01 PM
Did they ask for any adjustment to add floors at any point yet? Seen 1 to 2 added in a couple projects lately. Why go 44 when you can go 50 :p
01-25-2023, 10:06 PM
In the current market, I might have thought that a height reduction would be more likely.
02-02-2023, 08:26 PM
Crane base is in, sorry night time pictures while out for a walk.
02-02-2023, 08:58 PM
Any info on how sales are going? I struggle to understand how it can be a viable project.
02-02-2023, 10:42 PM
I read a report in the council minutes somewhere last year that said it sold out and sold out FAST
02-03-2023, 02:34 AM
(02-02-2023, 08:58 PM)panamaniac Wrote: Any info on how sales are going? I struggle to understand how it can be a viable project. Generally a building has to be at least 80-90% pre-sold to begin construction. I believe they got it sold before interest rates really started rising. I heard a number of purchasers were trying to back out, but legally they were committed (and assignment sale would be at a loss).
02-03-2023, 09:19 AM
02-03-2023, 09:52 AM
Great shot, way better than mine. Thank you. I assume you live in the near by building. Perhaps you can be our official photographer on this build for status updates ?
|