(05-18-2024, 09:24 PM)Lebronj23 Wrote: There has been no signs of any concerning delays. This should continue to climb barring a major financial issue with the developer. Some floors take longer than others based on a number of factors such as weather, contractor availability, material delivery schedule/logistics, holidays, slab floors, mechanical floors. They also sold these units at the absolute peak of the real estate market (Unfortunate for the buyer)
Nice. They're also back to 20 hour per day working hours since May 1.