In order to take advantage of all the great features that Waterloo Region Connected has to offer, including participating in the lively discussions below, you're going to have to register. The good news is that it'll take less than a minute and you can get started enjoying Waterloo Region's best online community right away.
or Create an Account




Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Public-Private Partnerships may not be the bargain we have been led to believe.
#16
I still hold that PPP is neither inherently good or inherently bad. It's fundamentally an outsourced contract, and how well it works out depends on (1) who the private party is, and (2) how well the contract is negotiated. It's the exact same situation for a private corporation that chooses to outsource part of its operations.

If we don't have bureaucrats who are good at negotiating business contracts, then that's one thing that should be addressed urgently.
Reply


#17
Empirical evidence in Ontario is that P3 costs more.

http://www.auditor.on.ca/en/reports_en/en14/305en14.pdf

You can hold all you want, those are the facts. To say it's because we have bureaucrats that aren't good at negotiating business contracts is neither here nor there. The fact its, P3 costs more. See Auditor General report.
Reply
#18
The AG's report doesn't say P3 is evil, nor does it says that Infrastructure Ontario should stop using this approach.  And it says the on-time completion record of P3 (one of the key objectives for choosing P3 in many cases) is very good.

They do recommend negotiating better contracts in the future.  Which is exactly what I said.  For example, AG says:

Quote:Infrastructure Ontario should ensure that all proposed changes to its VFM assessment methodology, including its plan to increase the base cost on the public-sector comparator side by up to 13.3% to reflect value-added innovations that the private sector may be bringing to projects, can be and are fully supported and can sustain scrutiny.

So what's your recommendation?
Reply
#19
Full disclosure of lifecycle payments and project costs so that an impartial assessment can be made.

I can say that at least 3 P3 partnerships in Ontario have resulted in increased operating costs. I am bound by NDAs to say no more than that. P3 partnerships, the way IO draws them up now, seems to reward private partners richly for only assuming part of the project risk.

It's a great gig. I've worked on the public side of a P3 deal, as well as the private side. The private side gets far more of the gravy.
Reply
« Next Oldest | Next Newest »



Forum Jump:


Users browsing this thread: 1 Guest(s)

About Waterloo Region Connected

Launched in August 2014, Waterloo Region Connected is an online community that brings together all the things that make Waterloo Region great. Waterloo Region Connected provides user-driven content fueled by a lively discussion forum covering topics like urban development, transportation projects, heritage issues, businesses and other issues of interest to those in Kitchener, Waterloo, Cambridge and the four Townships - North Dumfries, Wellesley, Wilmot, and Woolwich.