(02-17-2024, 06:54 PM)ZEBuilder Wrote:(02-17-2024, 01:18 PM)CP42 Wrote: Also out of curiosity, I assume you’re referring to the pieces on the bottom right they’re assembling?
What are these used for?
Those pieces they're assembling are often called fly forms or table forms. I don't know why they're building them now considering the podium still has to be built, podiums generally have abnormal floor plates because of parking ramps etc. That's why we're only just seeing them at TEK Tower. Once the tower gets to a repeated floor plate they'll typically start using them since it saves on having to build the form multiple times, you just pull it out and then lift it to the next floor and you can start rebar.
Thank you for the replies. I wonder if they're going to work more on the tower portion and take their time with the podium.