11-08-2023, 11:40 AM
(11-08-2023, 10:25 AM)KevinL Wrote: That still includes a roundabout at Westmount, yes?
It is still supposed to include the roundabout, digging through the 2024 Regional budget it appears that nearly 5 million is being asked for just the Westmount/Ottawa intersection in 2024 so it appears the roundabout might be constructed this summer. Then for the remaining Alpine to Fischer Hallman section they're asking for just over 3 million for 2024 and 4.5 million in 2025. So the roundabout might happen in 2024 and the rest of the project done in 2025, that is assuming the region approves the budget.