12-26-2023, 04:11 PM
I went by this today and there is activity on much of the site. The first phase buildings (stacked townhomes at the corner of Elmsdale and Ottawa) are all complete and Averton has now started on the second phase along Ottawa at the Fireside end of the property. They're using prebuilt wall and floor sections for this phase so there are piles of prebuilt sections throughout the site. They have foundations complete for multiple buildings and one of the new buildings is above grade.
Then at the rear of the site next to Elmsdale Park shoring work is partially completed for the two condos that JD Development Group is planning, they're marketing them as Verde Living. There isn't a lot of equipment on site so I didn't bother grabbing a picture but there is a tieback machine. They currently have a foundation/shoring/site servicing permit.
Then at the rear of the site next to Elmsdale Park shoring work is partially completed for the two condos that JD Development Group is planning, they're marketing them as Verde Living. There isn't a lot of equipment on site so I didn't bother grabbing a picture but there is a tieback machine. They currently have a foundation/shoring/site servicing permit.