12-31-2023, 05:03 PM
The trail is passable through the Google parking garage portion. Fences are down, but it's technically not "open" and a few parts aren't paved.
As Square said, no progress on Joseph St since UW is holding it up... Only going to be 2 years behind schedule at this point. That section of Joseph is almost free of traffic so it's ok, but the intersection crossing Victoria is nonsense without this trail.
I dont think this is technically the same project, but yes they will connect. As above, it's passable but it's not really done. I have seen a few people on it, but I think it will see more use once the Joseph St portion is done.
As Square said, no progress on Joseph St since UW is holding it up... Only going to be 2 years behind schedule at this point. That section of Joseph is almost free of traffic so it's ok, but the intersection crossing Victoria is nonsense without this trail.
(12-31-2023, 08:09 AM)ac3r Wrote: Is that the one that comes out behind Central Station? I have yet to see a single soul ever use that yet. I'm hoping that as more development goes up along Victoria it would see some use.
I dont think this is technically the same project, but yes they will connect. As above, it's passable but it's not really done. I have seen a few people on it, but I think it will see more use once the Joseph St portion is done.