Welcome Guest! In order to take advantage of all the great features that Waterloo Region Connected has to offer, including participating in the lively discussions below, you're going to have to register. The good news is that it'll take less than a minute and you can get started enjoying Waterloo Region's best online community right away. Click here to get started.


Thread Rating:
  • 2 Vote(s) - 3 Average
  • 1
  • 2
  • 3
  • 4
  • 5
King and Victoria Intermodal Station
King-Victoria Transit Hub Request for Qualifications Update
http://calendar.regionofwaterloo.ca/Coun...7#page=140

"The RFQ to shortlist potential developers will be advertised in early April and the selection process will be completed by August 2017. A Request for Proposal (RFP) will follow quickly after the RFQ process to ensure continuity and continued engagement from potential development teams."

"As with the ION LRT project, staff propose to establish a single point of contact during the entire procurement process. Staff recommend that the Director, Facilities & Fleet Management (or designated alternate) be designated as the sole contact for potential contractors wishing to contact staff and/or Councillors of the Region and local municipalities."
Everyone move to the back of the bus and we all get home faster.
Reply
Pre-qualification Request.   https://regionofwaterloo.bidsandtenders..../#Addendum
Reply
Many very qualified local taxpaying developers, general contractors and subcontractors unable to bid on this project due to The Region's labour status.

Only those who are associated with the carpenters union can participate.

It's a shame, but I guess the Region has tons of your money to spend on this project, the new bus facility in North Waterloo and now a renovation at the old courthouse for the police.

See page 40 of the open and fair RFP for the details.

Hamilton has the same status and is paying on average 20 % more for all of their projects
Reply
Thanks for pointing that out, and welcome to the forum, JeffH. Would you happen to know how many municipalities in Ontario are similarly bound? Is it something easily avoidable?
Reply
If it means decent benefits and better policing of safety standards, I'm good with it.
Reply
I don't like the term "carpentry" for something that should be a giant brutalist concrete monolith. Big Grin
For daily ion construction updates, photos and general urban rail news, follow me on twitter! @Canardiain
Reply
It's not easy to avoid, the Region tried quite hard. Some details in The Record at https://www.therecord.com/news-story/565...tion-bids/ and https://www.therecord.com/news-story/448...oo-region/ .

Normally I'm pretty pro-union, but this particular case I have zero support for the union. Two people putting up a garden shed on a Saturday signed union cards and the region ends up bound to hire only from their union for all future projects, costing tens of millions of dollars over the next decade. It's far too much power for such a small action.
Reply
(05-24-2017, 02:53 PM)taylortbb Wrote: It's not easy to avoid, the Region tried quite hard. Some details in The Record at https://www.therecord.com/news-story/565...tion-bids/ and https://www.therecord.com/news-story/448...oo-region/ .

Normally I'm pretty pro-union, but this particular case I have zero support for the union. Two people putting up a garden shed on a Saturday signed union cards and the region ends up bound to hire only from their union for all future projects, costing tens of millions of dollars over the next decade. It's far too much power for such a small action.

And I heard one of the two no longer works for the Region....

Coke
Reply
taylortbb, thanks a lot for the links, that was educational. Thanks again, Jeff, for bringing it up, I think it's something not many people are well-versed in (certainly that's the case for me).
Reply
[Image: 35626456350_9f6fcab894_b.jpg]

The Transit Hub Site has been cleared.
Reply
Just site prep? Request for proposals is still out there right?
Reply
(07-19-2017, 11:29 AM)Spokes Wrote: Just site prep?  Request for proposals is still out there right?

Correct. The old garage/ambulance station had finally fulfilled its use (it was an office/staging area during the underpass construction) and has now been removed.
My Twitter: @KevinLMaps
Reply
I would love to see some kind of a temporary park here, given that construction start is probably still at least 3-4 years away.
Reply
But that wouldn't be in keeping with Downtown Kitchener's longstanding tradition of fenced off gravel pits!
Reply
The pre-qualification stage closed on June 30th. Looks like there was only one submission from a team with EllisDon as the primary. Not sure if there is something with how the Region posts results to their website or if there was really only 1 pre-qual submission. This was supposed to narrow down the teams for the actual RFP.

https://regionofwaterloo.bidsandtenders....#Submitted