04-29-2019, 09:53 PM
(04-29-2019, 12:48 PM)ijmorlan Wrote: Yes, I think it’s safe to say that Bombardier’s part in the delay is all in the past. We’ve had all the vehicles for 4 months, and some of them for over a year. When was that pull-through test?
Not so fast...We heard in the council update from Feb 28
Quote:"Overall reliability of the vehicles continues to be an issue. Bombardier needs to
complete significant modifications to address reliability issues. This totals
approximately 50 to 100 hours per vehicle of critical work that needs to completed
before service starts and 200 to 250 hours of work that can be completed after
service starts. These types of issues can be expected with an initial run of vehicles."