11-09-2018, 03:24 PM
(11-09-2018, 02:44 PM)Pheidippides Wrote: Back in 2009 when the preferred mode was picked they thought the opening was going to be 2014:
“Opening 2014”
June 2009 - RAPID TRANSIT ENVIRONMENTAL ASSESSMENT PHASE 2, STEP 3b – PREFERRED RAPID TRANSIT SYSTEM OPTION AND STAGING PLAN
http://rapidtransit.regionofwaterloo.ca/...df#page=23
Fast-forward to 2012 when the LRV contract was awarded it had become was “early 2017”:
“Based on light rail ridership forecast, 14 light rail vehicles (LRVs) will be required to provide service in early 2017.”
June 2012 - STAGE 1 LIGHT RAIL TRANSIT: VEHICLE PROCUREMENT
http://rapidtransit.regionofwaterloo.ca/...pdf#page=1
It wasn’t until much later that “late 2017” started to appear in reports.
*sigh*...and in 2010 I chose to stay in the city because I thought I'd have LRT in a couple of years.