(11-04-2018, 08:20 PM)trainspotter139 Wrote: I can still see it happening for December. Once 511 is done debugging they can open the floodgates and let all the equipped trains out. They 505, 507, & 509 can get theirs installed
While I appreciate the optimism when I consider that the custom equipment for the other LRVs here in Waterloo started 113 days ago or 79 work days ago (on July 16) I can't imagine how it is possible to meet the December timeline.
Even if they can get the installation to a quarter of the first round of installation time, say 20 days, and work 7 days a week, you are still looking at November 25.
Even if they can finish testing the trackside signals and timing between now and then they would still have to fit in testing all the newly installed specialized equipment, burn-in time, simulated service, and other testing. I could see the remaining Kingston vehicles arriving before year-end, but even that seems unlikely at this point (I think 501 will be the hold up; and even when they remaining trains arrive they will have testing that needs to be done).
Again, I appreciate the optimism, and I hope I am wrong, but I cannot see it opening in December 2018 even with a reduced service level.
Everyone move to the back of the bus and we all get home faster.