05-30-2018, 12:46 PM
Here's the crux of it, since it hasn't yet been made public:
Vehicles in Waterloo Region:
Vehicles in Kingston:
Vehicles in Waterloo Region:
- 502 (Bombardier Owned Test Vehicle):
- Vehicle is assembled. Propulsion and braking routine testing 100% complete. Modifications are ongoing.
Vehicle used for Emergency Services Training and System Testing.
- GrandLinq On-Board Equipment Installation: Not yet installed
- Vehicle is assembled. Propulsion and braking routine testing 100% complete. Modifications are ongoing.
- 503 (Bombardier Owned Test Vehicle):
- Vehicle is assembled. Propulsion and braking routine testing 100% complete. Modifications are ongoing.
Vehicle used for System Testing.
- GrandLinq On-Board Equipment Installation: Not yet installed
- Vehicle is assembled. Propulsion and braking routine testing 100% complete. Modifications are ongoing.
- 504 (Bombardier Owned Test Vehicle):
- Vehicle is assembled. Propulsion and braking routine testing 100% complete. Modifications are ongoing.
Vehicle used for System Testing.
- GrandLinq On-Board Equipment Installation: Not yet installed
- Vehicle is assembled. Propulsion and braking routine testing 100% complete. Modifications are ongoing.
- 505 (Bombardier Owned Test Vehicle):
- Vehicle is assembled. Propulsion and braking routine testing 100% complete. Modifications are ongoing.
Vehicle used for System Testing.
- GrandLinq On-Board Equipment Installation: Not yet installed
- Vehicle is assembled. Propulsion and braking routine testing 100% complete. Modifications are ongoing.
- 506 (Bombardier Owned Test Vehicle):
- Vehicle is assembled. Propulsion and braking routine testing 100% complete. Modifications are ongoing.
Vehicle used for System Testing.
- GrandLinq On-Board Equipment Installation: Not yet installed
- Vehicle is assembled. Propulsion and braking routine testing 100% complete. Modifications are ongoing.
- 507 (Bombardier Owned Test Vehicle):
- Vehicle is assembled. Propulsion and braking routine testing 100% complete. Modifications are ongoing.
Vehicle used for System Testing.
- GrandLinq On-Board Equipment Installation: Not yet installed
- Vehicle is assembled. Propulsion and braking routine testing 100% complete. Modifications are ongoing.
Vehicles in Kingston:
- 501
- Vehicle was partially disassembled and is in process of modifications
- Routine Testing Status: Not yet started
- Production Status and Notes:
- Anticipated to be complete by June 8
- Target inspection week of June 11, 2018
- Anticipated to be complete by June 8
- GrandLinq On-Board Equipment Installation: Not yet installed
- Vehicle was partially disassembled and is in process of modifications
- 508
- Complete and inspected
- Routine Testing Status: 93%
- Production Status and Notes:
- Inspection complete (April 23, 2018)
- Undergoing Modifications
- Inspection complete (April 23, 2018)
- GrandLinq On-Board Equipment Installation: Not yet installed
- Complete and inspected
- 509
- Complete and inspected
- Routine Testing Status: 93%
- Production Status and Notes:
- Inspection complete (May 17, 2018)
- Undergoing Modifications
- Inspection complete (May 17, 2018)
- GrandLinq On-Board Equipment Installation: Not yet installed
- Complete and inspected
- 510
- Complete and inspected
- Routine Testing Status: 93%
- Production Status and Notes:
- Inspection complete (May 8, 2018)
- Undergoing Modifications
- Inspection complete (May 8, 2018)
- GrandLinq On-Board Equipment Installation: Not yet installed
- Complete and inspected
- 511
- Complete and inspected
- Routine Testing Status: 93%
- Production Status and Notes:
- Inspection complete (May 10, 2018)
- Undergoing Modifications
- Inspection complete (May 10, 2018)
- GrandLinq On-Board Equipment Installation: Not yet installed
- Complete and inspected
- 512
- Complete and inspection in progress
- Routine Testing Status: 76%
- Production Status and Notes:
- Testing in progress
- Inspection in Progress
- Testing and inspection to be completed by May 24, 2018
- Testing in progress
- GrandLinq On-Board Equipment Installation: Not yet installed
- Complete and inspection in progress
- 513
- Complete, inspection pending
- Routine Testing Status: 7%
- Production Status and Notes:
- Testing in progress, to be complete by May 25, 2018
- Target inspection week of May 28, 2018
- Testing in progress, to be complete by May 25, 2018
- GrandLinq On-Board Equipment Installation: Not yet installed
- Complete, inspection pending
- 514
- Under assembly, approximately 95% complete
- Routine Testing Status: Not yet started
- Production Status and Notes:
- Currently at interior fitting
- Anticipated to be complete assembly and testing by June 1, 2018
- Target inspection week of June 4, 2018
- Currently at interior fitting
- GrandLinq On-Board Equipment Installation: Not yet installed
- Under assembly, approximately 95% complete