(04-17-2018, 11:39 AM)KevinT Wrote: I'm curious, how do you propose that they could have delivered completed trains to the region any earlier when Metrolinx refused to sign off on a spec once the Transit City projects for which the original order was placed were all cancelled or delayed?
Even after they had a spec they could build and deliver to in mid-2016, the Communications Based Train Control signalling system remained unspecified, hence the hole in the dashboard we all witnessed at the open houses. I can only assume that that gap has been closed now, but it would only have happened very recently.
Unfortunately Bombardier can't blame Metrolinx as they are still a major customer of theirs, and the region can't blame Metrolinx as they still want Phase 2 funding, so the only party that gets publicly named and shamed is Bombardier. Are they blameless? I'm sure not, but I do feel sorry for them for getting 100% of the blame in the public press / mindset while only being partially responsible for the overall delays.
This should be a pinned post - thank you for explaining this so well Kevin!