12-20-2017, 06:39 PM
(12-20-2017, 05:23 PM)Canard Wrote: The million dollar question that nobody is asking: “Why aren’t the LRV’s being shipped, if they’re done?”
1) Shipping around Christmas proves unnecessarily challenging/costly?
2) Shipping completed units causes some degree of flustering with Toronto and its own desire for LRVs and streetcars?
3) Until you've proven that you can safely run a train along the entire line, there's not as much you can do, practically, to burn-in ever-more vehicles in the maintenance yard, and to that effect, GrandLinq hasn't likely set their rapidway clearing up, would have to do that, and then would have to get the region to show that it can keep the rapidway clear of cars, which in uptown it has decidedly not shown any ability to do?
4) Some software issue exists which would make them want to hold off on shipping until installed?