Light rail construction cost jumps $50M
Highlights:
Highlights:
- The region can only recover $4m from Bombardier in the original terms of the contract.
- The construction variance settlement with Grandlinq was $28.1m (60% of requested amount), surpassing the $12.4m contingency in the original $818m budget.
- The project was actually $10.9m under budget. (!)