(10-31-2017, 11:46 AM)timio Wrote: After a brief period of ramping up production, it appears as though Bombardier has fallen asleep. No more new deliveries for Ion this month and the TTC order has seemingly regressed in pace. I'm curious what the justification behind this is. QA? Paperwork? Labour challenges?
Not likely any thing Bombardier related at this point. 3-6 are fully assembled and for the past couple of weeks have been undergoing testing at Millhaven. The most likely cause for any delay at this point is shipment scheduling with CN as 3/4 have been ready to ship for 2 weeks now. We may not actually hear about any shipments from Bombardier until the last one actually ships. So we may end up playing a game of "Whats in GEXR Lancaster Yard" for the next couple of months or so.