I agree that for the number of trains that need to be delivered on a regular basis at the moment they only need flatbed is needed one.
But if it takes 10 days to get here presumably it takes 10 days to get back. So 20 days total between deliveries which is greater than the 14 days between LRV completions. That would mean at least 50 days until #2 gets here (10 days to here, 10 days back, 10 days to here, 10 days back, 10 days to here).
But if it takes 10 days to get here presumably it takes 10 days to get back. So 20 days total between deliveries which is greater than the 14 days between LRV completions. That would mean at least 50 days until #2 gets here (10 days to here, 10 days back, 10 days to here, 10 days back, 10 days to here).