(08-09-2017, 09:10 PM)tomh009 Wrote:(08-09-2017, 08:52 PM)Canard Wrote: Over the past couple of days, concrete stairs have been poured for the last-minute signal house that was added just South of the Kitchener Market station.
...yeah, I know, that's the point we're at for updates. It's a good thing: things are wrapping up!
So was this signal house an afterthought? It just appeared one day ...
Yep - the concrete got all jackhammered out, all the way from Kitchener Market to Cameron... all new conduits were laid in, and covered back up - huge job with tons of rework over many weeks after everything was all done. Definitely something that was missed in the original design.
jwilliamson - thanks for the photo! They made quick work of that, although with it being just 3 pieces, it really shouldn't have taken more than a few hours to get up and installed.