(02-28-2017, 10:46 AM)Viewfromthe42 Wrote: I am curious how the deficiencies repair aligns with timelines and closures for final asphalt layers, since I don't think anywhere with new curbs actually has the asphalt up to even with the bottom surface of the curb.
Final asphalt laying will occur sometime closer to the end of construction and will most likely occur at night so as to not require closure of the roads during business hours.