Lots of work happening to tidy up loose ends on Charles. No sign as of yet of finishing the concrete between Queen and Ontario, though. And some welding still needs to be done in front of Cameron Heights.
Between Queen and Benton: New concrete strip between the tracks and the curbs.
At Cedar: Intersection closed and almost ready to pour the concrete.
Between Stirling and Borden: Working on the forms so the concrete can be poured
Between Queen and Benton: New concrete strip between the tracks and the curbs.
At Cedar: Intersection closed and almost ready to pour the concrete.
Between Stirling and Borden: Working on the forms so the concrete can be poured