04-17-2016, 07:54 PM
Up toward Block Line, the hillside still needs to be widened with retaining walls. Those are well under way but there's clearly more work to come.
The additional area in the foreground is for the eventual traction substation.
On the north side of Block Line, where the station will go, retaining walls are not being used - just a very large amount of fill. This is also still under way.
Courtland goes back to two-way traffic north of Block Line.
The additional area in the foreground is for the eventual traction substation.
On the north side of Block Line, where the station will go, retaining walls are not being used - just a very large amount of fill. This is also still under way.
Courtland goes back to two-way traffic north of Block Line.