In order to take advantage of all the great features that Waterloo Region Connected has to offer, including participating in the lively discussions below, you're going to have to register. The good news is that it'll take less than a minute and you can get started enjoying Waterloo Region's best online community right away.
or Create an Account




Thread Rating:
  • 15 Vote(s) - 3.93 Average
  • 1
  • 2
  • 3
  • 4
  • 5
ION - Waterloo Region's Light Rail Transit
Ion update to council in planning agenda for next week:
http://www.regionofwaterloo.ca/en/region...df#page=39

Not much we haven't heard before:
"the Region and GrandLinq’s goal continues to focus on service launch in late 2017."
"Delivery of vehicles is currently scheduled to be delayed by two months to October 2016 for the first vehicle and by four months to May 2017 for the fourteenth vehicle from the original delivery schedule."
"A web page dedicated to Stage 2 ION has been created and can be accessed at www.stage2ION.ca"

Latest expenditures to date:
http://www.regionofwaterloo.ca/en/region...df#page=51

Construction milestones
 Of the 36,000 metres of LRT track required for ION, more than 8,600 metres of
track has been placed since the start of construction. The remaining LRT track is
expected to be placed this year
 Construction of the King Street grade separation bridge is well underway. On
March 5, 2016, the major concrete pour for the bridge deck took place. This
required pouring close to 800 cubic metres of concrete. This was achieved with
the assistance of a climate controlled structure, which allowed crews to complete
critical temperature-sensitive work. On March 5 and March 6, during the major
concrete pour, the outside temperature had dropped to minus 12 degrees
Celsius
 Installation of TPSS (Traction Power Substations) stations has taken place at
Northfield, Bearinger and Columbia. The TPSS convert commercial alternatingcurrent
electricity into direct-current electricity that is required to power the
light rail vehicles
 Construction on the OMSF has been proceeding well with completion expected
later this year
 Over 50% of municipal underground utility (watermains, sanitary sewer, storm
sewer) replacements have been completed with work in UpTown Waterloo,
Downtown Kitchener and Courtland remaining
 The majority of other utility work (electrical, natural gas, communications) is also
complete with some areas expected to be completed early in the 2016
construction season
 Over 5,000 metres of roadway have been restored
 Eight of ten bridges/culverts have now been placed, including the pedestrian
bridge over Montgomery Creek on Courtland Avenue and the Laurel Creek
culvert in Waterloo Park
 Foundations have been placed for five ION stops
 Communications milestones and statistics are included below
Everyone move to the back of the bus and we all get home faster.
Reply
« Next Oldest | Next Newest »



Messages In This Thread
RE: ION - Waterloo Region's Light Rail Transit - by Pheidippides - 04-08-2016, 04:00 PM
[No subject] - by Spokes - 08-28-2014, 04:16 PM

Forum Jump:


Users browsing this thread: 102 Guest(s)

About Waterloo Region Connected

Launched in August 2014, Waterloo Region Connected is an online community that brings together all the things that make Waterloo Region great. Waterloo Region Connected provides user-driven content fueled by a lively discussion forum covering topics like urban development, transportation projects, heritage issues, businesses and other issues of interest to those in Kitchener, Waterloo, Cambridge and the four Townships - North Dumfries, Wellesley, Wilmot, and Woolwich.

              User Links