03-14-2016, 09:50 AM
GrandLinq might be finished up their end in April 2017, sure - but as I've mentioned before, testing will take 6-9 months of train movements. So you can back-calculate from that...
We will not be riding full service on ion in April 2017. There's just no way. Victoria/King and Waterloo aren't going to wrap up until the end of 2016, so April 2017 is just four months past that.
I really, really hope you're right, though! I would much prefer the opening ceremony is held in spring/summer than winter. I hate the idea of balloons and streamers and a band playing in the snow.
We will not be riding full service on ion in April 2017. There's just no way. Victoria/King and Waterloo aren't going to wrap up until the end of 2016, so April 2017 is just four months past that.
I really, really hope you're right, though! I would much prefer the opening ceremony is held in spring/summer than winter. I hate the idea of balloons and streamers and a band playing in the snow.