Fairview Mall Transit Terminal $2,000,000 August 2, 2016
University of Waterloo Transit Plaza $2,531,000 August 2, 2016
Northfield Drive Transit Facility $775,000 January 1, 2017
iXpress Station Development $3,535,000 August 2, 2016
Blockline Station Development $2,000,000 August 2, 2016
Vehicle Replacements $12,000,000 August 2, 2016
Fairview Mall Transit Terminal $2,000,000 August 2, 2016
University of Waterloo Transit Plaza $2,531,000 August 2, 2016
Northfield Drive Transit Facility $775,000 January 1, 2017
iXpress Station Development $3,535,000 August 2, 2016
Blockline Station Development $2,000,000 August 2, 2016
Vehicle Replacements $12,000,000 August 2, 2016
(08-23-2016, 11:13 AM)Markster Wrote: I think they mean literally building ("developing") bus stations/platforms.How are they going to spend $3.5 million at the Ottawa street stop, it is one of the least used stops that I have seen.
The list basically reads as "GRT's Capital Plan for 2016/2017"
Which would mean that "iXpress Station Development" is probably referring to the Ottawa iXpress platforms/shelters.
The "Block Line Station Development" would be the bus loop and station at the ION station there, which I guess was not part of the ION project agreement.