04-11-2019, 07:16 AM
(04-10-2019, 09:28 PM)embe Wrote:(04-10-2019, 08:33 PM)ijmorlan Wrote: I hope they installed the right pipes and conduit into the space before pouring! Not easy to correct any mistakes later…
Are there types of pipe/conduit that would need to be located that far down?
With the amount of rebar and size of a pit I figured it would be a few more days of truck loads, but can't say I've seen a foundation/footing like that before.
I thought I saw pipes within the rebar. It looked to me like it might be drainage pipes. I also thought I might have seen some electrical conduit. But I don’t really know for sure.