In order to take advantage of all the great features that Waterloo Region Connected has to offer, including participating in the lively discussions below, you're going to have to register. The good news is that it'll take less than a minute and you can get started enjoying Waterloo Region's best online community right away.
or Create an Account




Thread Rating:
  • 15 Vote(s) - 3.93 Average
  • 1
  • 2
  • 3
  • 4
  • 5
ION - Waterloo Region's Light Rail Transit
I think there's a lot of unjustified fear here, unless Bombardier continues to slip, even if LRT2 comes in late September, and they only hit their original cadence we'll have all the LRTs by Jan/Feb 2018, and then we should be able to launch a month or two after that.....that's till "very early Spring 2018".

The only circumstances where a "Late 2018" launch becomes a thing is if Bombardier continues to not deliver any trains until at least mid 2018.  By then, I'm quite sure we'd be in the middle of legal action against them.
Reply


Hilariously, Bombardier just tweeted this photo of a cab for Edmonton's Valley Line:

<blockquote class="twitter-tweet" data-lang="en"><p lang="en" dir="ltr">A sneak peek into the manufacturing of the <a href="https://twitter.com/yegvalleyLRT">@yegvalleyLRT</a>. Picture of the cab for Edmonton's LRT vehicle #1. Progress is on schedule. <a href="https://twitter.com/hashtag/YEG?src=hash">#YEG</a> <a href="https://t.co/86hn6uvQE0">pic.twitter.com/86hn6uvQE0</a></p>&mdash; BombardierRail (@BombardierRail) <a href="https://twitter.com/BombardierRail/status/877201934624722944">June 20, 2017</a></blockquote>

The timing could not be worse or more infuriating.
Reply
CTV now reporting as well:

Progress on first Ion vehicle, arrival of remaining vehicles both behind schedule
Reply
(06-20-2017, 12:24 PM)danbrotherston Wrote: I think there's a lot of unjustified fear here, unless Bombardier continues to slip, even if LRT2 comes in late September, and they only hit their original cadence we'll have all the LRTs by Jan/Feb 2018, and then we should be able to launch a month or two after that.....that's till "very early Spring 2018".

The only circumstances where a "Late 2018" launch becomes a thing is if Bombardier continues to not deliver any trains until at least mid 2018.  By then, I'm quite sure we'd be in the middle of legal action against them.

I fully admit I could just be influenced by media 'sensationalism', but isn't it completely justified to fear that Bombardier will continue to slip?  

Even looking at a statement like: "even if LRT2 comes in late September, and they only hit their original cadence" - this doesn't seem like the likely worst case at all.  They've never (?) hit their projected cadence, so I'm don't really have any faith that they'll hit their projected cadence in the future either.

I think it really sucks, to be honest.  It's more time for people to bitch and moan about the LRT.  It's more ammunition for how Government can't do anything right.  Yadda, yadda, yadda.
Reply
Spring 2018? so much for early (jan/feb) 2018. Grrr
Reply
Minor nitpick (since I'm seeing it more and more, including on the media articles):

LRT = Light Rail Transit, or Light Rapid Transit: The System
LRV = Light Rail Vehicle: The thing that goes on the tracks (trains)

I'm just so baffled that Berlin and Dandenong (Melbourne) can crank out LRV's left and right, and we just can't seem to do it here at all.
Reply
Somehow Bombardier's smooth expertise elsewhere in the world failed to fully translate to North America.
Reply


(06-20-2017, 01:58 PM)KevinL Wrote: Somehow Bombardier's smooth expertise elsewhere in the world failed to fully translate to North America.

It’s quite extraordinary. At this point, their estimates don’t mean anything. Only Charlie Brown would believe them.

I don’t believe they have ever done as promised with modern Canadian LRV/Streetcar deliveries. And by that, I mean they haven’t even met a revised revised revised revised schedule, never mind the original schedule. Keep in mind the original Waterloo schedule should have had all the vehicles delivered last year, in 2016; and there should be over 100 Toronto streetcars delivered. Furthermore, they have provided misleading and incorrect explanations for the delays.
Reply
I am pre-emptively dreading the Facebook comments about this.
Reply
At least there's one winner in all this...Grandlinq. They will be dancing all the way to the bank. Per the project agreement, the Region has to begin paying them as soon as they reach substantial completion, whether we have vehicles or not. And our measly 21,000/day entitlement from Bombardier doesn't nearly cover that amount.
Reply
(06-20-2017, 01:23 PM)SammyOES2 Wrote: I fully admit I could just be influenced by media 'sensationalism', but isn't it completely justified to fear that Bombardier will continue to slip?  

Even looking at a statement like: "even if LRT2 comes in late September, and they only hit their original cadence" - this doesn't seem like the likely worst case at all.  They've never (?) hit their projected cadence, so I'm don't really have any faith that they'll hit their projected cadence in the future either.

I think it really sucks, to be honest.  It's more time for people to bitch and moan about the LRT.  It's more ammunition for how Government can't do anything right.  Yadda, yadda, yadda.

I agree, and am frustrated by the ammunition to people to complain about government not doing anything right etc.

I acknowledge that Bombardier might not hit their planned cadence....but they are still claiming too be able to do so. Producing 14 trains is easier than 214, and they have in fact hit their planned deliveries for the TTC street car this year.

It is entirely possible they'll continue to miss, but I'm not ready to say that's the case for sure as others seem to be.

@Bob_McBob This is one thing I'm certain we can all agree on.
Reply
And here we go...

https://www.facebook.com/ctvkitchener/po...8282039793
Reply
Not to mention that the first LRV was supposed to be undergoing dynamic testing by now...
Reply


I CANT HANDLE THIS

<blockquote class="twitter-tweet" data-lang="en"><p lang="en" dir="ltr">It's like an ANGRY DEATH LRV and it's going to melt your face off ? <a href="https://t.co/zIqf2m50lc">pic.twitter.com/zIqf2m50lc</a></p>&mdash; iain (@Canardiain) <a href="https://twitter.com/Canardiain/status/877323524561543168">June 21, 2017</a></blockquote>
Reply
(06-20-2017, 08:34 PM)Canard Wrote: I CANT HANDLE THIS

I'm pretty sure that's the Dip Machine from Who Framed Roger Rabbit

Reply
« Next Oldest | Next Newest »



Forum Jump:


Users browsing this thread: 29 Guest(s)

About Waterloo Region Connected

Launched in August 2014, Waterloo Region Connected is an online community that brings together all the things that make Waterloo Region great. Waterloo Region Connected provides user-driven content fueled by a lively discussion forum covering topics like urban development, transportation projects, heritage issues, businesses and other issues of interest to those in Kitchener, Waterloo, Cambridge and the four Townships - North Dumfries, Wellesley, Wilmot, and Woolwich.

              User Links