(08-08-2016, 10:23 AM)Canard Wrote: That's great news. With the curbs already in on Charles, between Ottawa and Borden, we might see some good progress here over the next month (ie, total finalization).
Hopefully the work will continue onto Ottawa, which is currently roughly graded, but still needs curbs, sidewalks, (light and cat) pole foundations, pavement -- and the embedded track!
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
08-08-2016, 12:05 PM
(This post was last modified: 08-08-2016, 12:09 PM by Canard.)
Is Ottawa wet-utility complete, though? I haven't been down Ottawa proper in a few weeks to investigate. I was under the impression that all of the above was still a few months away.
Posts: 10,282
Threads: 65
Joined: Sep 2014
Reputation:
296
Apparently, yes, given that they are (supposedly) preparing for the base coat of asphalt (haven't seen much activity though) on Ottawa. And Ottawa is supposed to open mid-August, that's only about a week away.
Clearly the embedded track and the sidewalks won't be done by then. Hopefully at least the curbs will be in place.
Posts: 2,015
Threads: 11
Joined: Oct 2014
Reputation:
77
The beams supporting the roof and the roof supports for the Laurier-Waterloo Park are now in. I'll see if I can get a photo on my way home. Actually looks like a station! Ironic that the station that will likely have the least utility in the system seems to be getting a lot of the "firsts."
Everyone move to the back of the bus and we all get home faster.
Posts: 2,163
Threads: 17
Joined: Sep 2014
Reputation:
76
(08-08-2016, 01:45 PM)Pheidippides Wrote: The beams supporting the roof and the roof supports for the Laurier-Waterloo Park are now in. I'll see if I can get a photo on my way home. Actually looks like a station! Ironic that the station that will likely have the least utility in the system seems to be getting a lot of the "firsts."
If anything, that's the one I would choose to do first. It's the least disruptive for any remediation.
Posts: 4,401
Threads: 15
Joined: Aug 2014
Reputation:
124
(08-08-2016, 01:45 PM)Pheidippides Wrote: The beams supporting the roof and the roof supports for the Laurier-Waterloo Park are now in. I'll see if I can get a photo on my way home. Actually looks like a station! Ironic that the station that will likely have the least utility in the system seems to be getting a lot of the "firsts."
I think that may be on purpose - if anything needs to be corrected, adjusted, reworked, etc it's on a low-use structure where it will not have a heavy impact.
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
08-08-2016, 05:30 PM
(This post was last modified: 08-08-2016, 05:31 PM by Canard.)
Latest ion update has lots of goodies:
- ION stop and driver’s facility at Conestoga Mall
- The new lot on the north side of the track at Seagram has been paved
- Installation of the frame for the Willis Way anchor wall
- Work has commenced on the Northbound Central Station LRT stop at the King Street Grade Separation
- (Borden) Landscaping and the installation of sidewalks, as well as the overhead catenary system
- Work at the Huron Spur/Borden will commence on or about August 22 to continue the track from Borden onto the Huron Spur
- Ottawa/Mill intersection closure will be extended and will now re-open on or about October 15
- Block Line/Courtland will close on or about August 15 for approximately two months. A detour will be in place via Manitou to Bleams to Homer Watson
Very fascinated by the stop work under the grade sep. It's so hard to see what's going on there, especially since the connection path in front of Google is now closed.
Posts: 2,015
Threads: 11
Joined: Oct 2014
Reputation:
77
Everyone move to the back of the bus and we all get home faster.
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
Posts: 4,401
Threads: 15
Joined: Aug 2014
Reputation:
124
Is there a reason the pole bases are sunk into the concrete? Will they be refilled, or covered somehow? If they fill with water, will this be a problem if there's a sudden freeze?
Posts: 10,282
Threads: 65
Joined: Sep 2014
Reputation:
296
(08-08-2016, 07:35 PM)Canard Wrote: Top-notch fabrication here - beautiful welds and finish on this! If only the weldments I designed could come back to our shop this nice.
Agreed, very nice indeed!
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
08-08-2016, 09:18 PM
(This post was last modified: 08-08-2016, 09:19 PM by Canard.)
(08-08-2016, 08:49 PM)KevinL Wrote: Is there a reason the pole bases are sunk into the concrete? Will they be refilled, or covered somehow? If they fill with water, will this be a problem if there's a sudden freeze?
They'll be covered for sure, if not filled with concrete. They don't just leave things like that exposed. The top surface of the concrete is not the final finish, either.
Posts: 516
Threads: 1
Joined: Sep 2014
Reputation:
20
(08-08-2016, 01:45 PM)Pheidippides Wrote: Actually looks like a station! Ironic that the station that will likely have the least utility in the system seems to be getting a lot of the "firsts."
No bias in your evaluation of this station (seeing RED above) ... Your view does not mean that this is a quid pro quo for the real world. Yes even bias can be ironic
Posts: 4,401
Threads: 15
Joined: Aug 2014
Reputation:
124
Not very busy on Frederick when I passed by earlier - but it was certainly well lit.
Posts: 170
Threads: 1
Joined: Aug 2014
Reputation:
10
Walked by the freight rail crossing King in Uptown tonight and looks like it's connected to the northbound ION line now!
|