09-16-2016, 02:29 PM
They only have the small section of Erb left to pave and the little wedge between the nb and SB tracks. There is one little gap in the embedded SB track that needs another weld still.
As i mentioned the other day the antique looking lights of uptown were extended to John, but beyond that, south of John, they have installed the overhead lights with the LED fixtures.
Almost all the cat poles are now in between William and union or should be by end of day.
Lots of landscaping progress between Wellington and union along king.
The grh TPSS site seems nearly prepped for it to be installed.
As i mentioned the other day the antique looking lights of uptown were extended to John, but beyond that, south of John, they have installed the overhead lights with the LED fixtures.
Almost all the cat poles are now in between William and union or should be by end of day.
Lots of landscaping progress between Wellington and union along king.
The grh TPSS site seems nearly prepped for it to be installed.
Everyone move to the back of the bus and we all get home faster.