08-06-2016, 09:52 PM
(08-06-2016, 09:10 PM)519 Wrote: My understanding is that the plan was approved by the city. During the process It was slightly modified from the original design.. adding more setback (not as much as Owen wanted) but also added a few more floors to each tower (was 15 and 19). The challenge at the city level was unsuccessful which lead to the OMB appeal.
They have enough sales to start based on their spring news letter.
My guess is they will start ASAP. Winter is Coming. Lol.
you re incorrect as you cannot approve a plan without zoning in place which is why this went to omb in the first place...if the zoning was in place there would have been no omb process as you cannot appeal a site plan it is being built per the as of right zoning....