(04-26-2016, 09:34 AM)zanate Wrote:Yes, but the LRT train tunnel under the expressway - paid by the LRT project- extended the construction by one year. This was not part of the 2011 time line estimates for finishing the project.(04-26-2016, 08:48 AM)KW65 Wrote: See: http://www.mto.gov.on.ca/english/travell...t2011-3003
Oooh. And look what the Wayback Machine says. http://web.archive.org/web/2011112423544...t2011-3003
Current estimated end of work date: Oct 2016.
Estimated end of work date in 2011: July 2015.