I just walked by there and saw the pavement markings. It looks like a ~4.5m width sidewalk is going down to about ~3.0 m where the black wall is. It does not appear as though this will be a significant bottleneck. It may appear so because the whole are is very sidewalk-heavy, but this new restricted path is still far wider than most sidewalks typically are.
Posts: 1,094
Threads: 3
Joined: Aug 2015
Reputation:
57
Was walking along side the Kaufman Lofts @ Francis today. They've only been working on the section for what, 1 week, maybe 2 now? Yet they already had a cat pole foundation in next to the Lofts. Kind of strange considering the minimum 3 months still left on this road closure.
Even stranger still, the foundation was on the west side of the road, when track here is supposed to be running on the east side. Anyone know why that might be?
Posts: 668
Threads: 2
Joined: Oct 2014
Reputation:
24
(05-11-2016, 06:56 PM)GtwoK Wrote: Was walking along side the Kaufman Lofts @ Francis today. They've only been working on the section for what, 1 week, maybe 2 now? Yet they already had a cat pole foundation in next to the Lofts. Kind of strange considering the minimum 3 months still left on this road closure.
Even stranger still, the foundation was on the west side of the road, when track here is supposed to be running on the east side. Anyone know why that might be?
New traffic poles?
Posts: 1,094
Threads: 3
Joined: Aug 2015
Reputation:
57
Ah, that could be. They might have on set back because the curve of the road reduces visibility. Still a bit premature for any sort of foundation though, I would think.
Posts: 4,401
Threads: 15
Joined: Aug 2014
Reputation:
124
From this morning - sidewalk pour at Charles and Ontario.
Posts: 2,015
Threads: 11
Joined: Oct 2014
Reputation:
77
King at William this morning:
Everyone move to the back of the bus and we all get home faster.
Posts: 1,094
Threads: 3
Joined: Aug 2015
Reputation:
57
That's supposed to open on Monday?
Posts: 165
Threads: 1
Joined: Nov 2014
Reputation:
7
I was wondering about that this morning, as well.
Posts: 4,401
Threads: 15
Joined: Aug 2014
Reputation:
124
If they work through the weekend I would say it's doable.
Posts: 165
Threads: 1
Joined: Nov 2014
Reputation:
7
They have paved the intersection of Caroline and Allen.
Posts: 1,094
Threads: 3
Joined: Aug 2015
Reputation:
57
Really? That's not supposed to be done until Mid-June! Is track laid and everything?
Posts: 4,401
Threads: 15
Joined: Aug 2014
Reputation:
124
Track does not go through that intersection per se, so perhaps it hasn't?
Posts: 1,084
Threads: 2
Joined: Aug 2014
Reputation:
31
05-12-2016, 01:34 PM
(This post was last modified: 05-12-2016, 01:35 PM by timio.)
Track will only go across the north side of the intersection and along the north side of Allen, so the intersection proper could be done with only the track left to lay once the rest of Allen is ready.
*edit for tense
Posts: 2,163
Threads: 17
Joined: Sep 2014
Reputation:
76
True. Gaukel was reopened without tracks. It was closed again later, and a strip of asphalt was taken out to allow building of the track.
Posts: 1,191
Threads: 0
Joined: Mar 2015
Reputation:
34
I saw a crew installing crossing gates at Columbia today.
|