Waterloo Region Connected
ION - Waterloo Region's Light Rail Transit - Printable Version

+- Waterloo Region Connected (https://www.waterlooregionconnected.com)
+-- Forum: Waterloo Region Works (https://www.waterlooregionconnected.com/forumdisplay.php?fid=14)
+--- Forum: Transportation and Infrastructure (https://www.waterlooregionconnected.com/forumdisplay.php?fid=25)
+--- Thread: ION - Waterloo Region's Light Rail Transit (/showthread.php?tid=14)

Pages: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 252 253 254 255 256 257 258 259 260 261 262 263 264 265 266 267 268 269 270 271 272 273 274 275 276 277 278 279 280 281 282 283 284 285 286 287 288 289 290 291 292 293 294 295 296 297 298 299 300 301 302 303 304 305 306 307 308 309 310 311 312 313 314 315 316 317 318 319 320 321 322 323 324 325 326 327 328 329 330 331 332 333 334 335 336 337 338 339 340 341 342 343 344 345 346 347 348 349 350 351 352 353 354 355 356 357 358 359 360 361 362 363 364 365 366 367 368 369 370 371 372 373 374 375 376 377 378 379 380 381 382 383 384 385 386 387 388 389 390 391 392 393 394 395 396 397 398 399 400 401 402 403 404 405 406 407 408 409 410 411 412 413 414 415 416 417 418 419 420 421 422 423 424 425 426 427 428 429 430 431 432 433 434 435 436 437 438 439 440 441 442 443 444 445 446 447 448 449 450 451 452 453 454 455 456 457 458 459 460 461 462 463 464 465 466 467 468 469 470 471 472 473 474 475 476 477 478 479 480 481 482 483 484 485 486 487 488 489 490 491 492 493 494 495 496 497 498 499 500 501 502 503 504 505 506 507 508 509 510 511 512 513 514 515 516 517 518 519 520 521 522 523 524 525 526 527 528 529 530 531 532 533 534 535 536 537 538 539 540 541 542 543 544 545 546 547 548 549 550 551 552 553 554 555 556 557 558 559 560 561 562 563 564 565 566 567 568 569 570 571 572 573 574 575 576 577 578 579 580 581 582 583 584 585 586 587 588 589 590 591 592 593 594 595 596 597 598 599 600 601 602 603 604 605 606 607 608 609 610 611 612 613 614 615 616 617 618 619 620 621 622 623 624 625 626 627 628 629 630 631 632 633 634 635 636 637 638 639 640 641 642 643 644 645 646 647 648 649 650 651 652 653 654 655 656 657 658 659 660 661 662 663 664 665 666 667 668 669 670 671 672 673 674 675 676 677 678 679 680 681 682 683 684 685 686 687 688 689 690 691 692 693 694 695 696 697 698 699 700 701 702 703 704 705 706 707 708 709 710 711 712 713 714 715 716 717 718 719 720 721 722 723 724 725 726 727 728 729 730 731 732 733 734 735 736 737 738 739 740 741 742 743 744 745 746 747 748 749 750 751 752 753 754 755 756 757 758 759 760 761 762 763 764 765 766 767 768 769 770 771 772 773 774 775 776 777 778 779 780 781 782 783 784 785 786 787 788 789 790 791 792 793 794 795 796 797 798 799 800 801 802 803 804 805 806 807 808 809 810 811 812 813 814 815 816 817 818 819 820 821 822 823 824 825 826 827 828 829 830 831 832 833 834 835 836 837 838 839 840 841 842 843 844 845 846 847 848 849 850 851 852 853 854 855 856 857 858 859 860 861 862 863 864 865 866 867 868 869 870 871 872 873 874 875 876 877 878 879 880 881 882 883 884 885 886 887 888 889 890 891 892 893 894 895 896 897 898 899 900 901 902 903 904 905 906 907 908 909 910 911 912 913 914 915 916 917 918 919 920 921 922 923 924 925 926 927 928 929 930 931 932 933 934 935 936 937 938 939 940 941 942 943 944 945 946 947 948 949 950 951 952 953 954 955 956 957 958 959 960 961 962 963 964 965 966 967 968 969 970 971 972 973 974 975 976 977 978 979 980 981 982 983 984 985 986 987 988 989 990 991 992 993 994 995 996 997 998 999 1000 1001 1002 1003 1004 1005 1006 1007 1008 1009 1010 1011 1012 1013 1014 1015 1016 1017 1018 1019 1020 1021 1022 1023 1024 1025 1026 1027 1028 1029 1030 1031 1032 1033 1034 1035 1036 1037 1038 1039 1040 1041 1042 1043 1044 1045 1046 1047 1048 1049 1050 1051 1052 1053 1054 1055 1056 1057 1058 1059 1060 1061 1062 1063 1064 1065 1066 1067 1068 1069 1070 1071 1072 1073 1074 1075 1076 1077 1078 1079 1080 1081 1082 1083 1084 1085 1086 1087 1088 1089 1090 1091 1092 1093 1094 1095 1096 1097 1098 1099 1100 1101 1102 1103 1104 1105 1106 1107 1108 1109 1110 1111 1112 1113 1114 1115 1116 1117 1118 1119 1120 1121 1122 1123 1124 1125 1126 1127 1128 1129 1130 1131 1132 1133 1134 1135 1136 1137 1138 1139 1140 1141 1142 1143 1144 1145 1146 1147 1148 1149 1150 1151 1152 1153 1154 1155 1156 1157 1158 1159 1160 1161 1162 1163 1164 1165 1166


RE: ION - Waterloo Region's Light Rail Transit - taylortbb - 01-07-2023

(01-06-2023, 06:20 PM)danbrotherston Wrote: These are supposed to be experts...they should know about this before hand.

There was an interesting comment on Reddit in reply to Cory, https://www.reddit.com/r/waterloo/comments/1050ifq/response_to_email_about_ion_going_offline_in_the/j38l4d5/?context=1 . I have no idea if it's true, and 50% increase in capital cost seems like an exaggeration, but I do remember that there's some sections of the route (at least King/Victoria) that are right at the maximum possible grade for the Flexity Freedom. So it seems at least somewhat plausible.

The comment in full is:
Quote:My (unofficial) understanding is that the route itself is problematic for adverse weather. Specifically, that the grade in places is steeper than the trains can be expected to climb in icing conditions. Fixing this would have required a route change which would have increased the entire ion cost by 50% or more.

The decision was made that the local economic cost of shutting it down for a day or every year or two was more palatable than increasing the project cost by that amount. Also, since they expected to be shut down in icy weather due to the grade, they didn't initially invest in other features which would allow operation in those conditions if the grade weren't an issue (ie. catenary scrapers).

Assuming this isn't exaggerated (I heard it during a casual conversation), it actually all seems pretty reasonable to me. The economic case for increasing capital expenditures by 50% in order to increase reliability from 98% to 98.25% (or whatever it would have been) is pretty weak.

However, it seems like the grade has actually been less of an issue than they originally thought, meaning that the bottleneck to operation in these conditions has been the other equipment they chose not to buy. This has the appearance of poor planning, when they actually just made a reasonable decision based on operating expectations.



RE: ION - Waterloo Region's Light Rail Transit - ac3r - 01-07-2023

So the trains are garbage as well as the engineering. No surprise given that they were from Bombardier and overall the project leaders tried to save every cent they could, resulting in a "rapid transit" system that shuts down in the winter, can't climb minor inclines and moves extremely slowly.

You get what you pay for.


RE: ION - Waterloo Region's Light Rail Transit - danbrotherston - 01-07-2023

(01-07-2023, 12:27 PM)taylortbb Wrote:
(01-06-2023, 06:20 PM)danbrotherston Wrote: These are supposed to be experts...they should know about this before hand.

There was an interesting comment on Reddit in reply to Cory, https://www.reddit.com/r/waterloo/comments/1050ifq/response_to_email_about_ion_going_offline_in_the/j38l4d5/?context=1 . I have no idea if it's true, and 50% increase in capital cost seems like an exaggeration, but I do remember that there's some sections of the route (at least King/Victoria) that are right at the maximum possible grade for the Flexity Freedom. So it seems at least somewhat plausible.

The comment in full is:
Quote:My (unofficial) understanding is that the route itself is problematic for adverse weather. Specifically, that the grade in places is steeper than the trains can be expected to climb in icing conditions. Fixing this would have required a route change which would have increased the entire ion cost by 50% or more.

The decision was made that the local economic cost of shutting it down for a day or every year or two was more palatable than increasing the project cost by that amount. Also, since they expected to be shut down in icy weather due to the grade, they didn't initially invest in other features which would allow operation in those conditions if the grade weren't an issue (ie. catenary scrapers).

Assuming this isn't exaggerated (I heard it during a casual conversation), it actually all seems pretty reasonable to me. The economic case for increasing capital expenditures by 50% in order to increase reliability from 98% to 98.25% (or whatever it would have been) is pretty weak.

However, it seems like the grade has actually been less of an issue than they originally thought, meaning that the bottleneck to operation in these conditions has been the other equipment they chose not to buy. This has the appearance of poor planning, when they actually just made a reasonable decision based on operating expectations.

Yeah, the 50% increase seems silly. If the incline at King/Victoria was really a problem it could have been reduced significantly by making the King/Victoria station a centre of the road station, then by restricting cross and turning traffic at Moore and Wellington (something that would have had minimal impact on car trips given Weber and Agnes), and then sinking the tracks into the road up to Agnes to make the slope more gradual.

More expensive...sure....425 million...uhh...not even close.

But I'm guessing this is more to do with the in-feasibility of restricting cars than the actual cost.

In any case, it sounds like the problem is not the incline anyway...but other operational issues.

Again, I would like to know what the point of hiring an expensive contractor to handle these things.....it's supposed to be expertise, but we don't seem to be getting that.


RE: ION - Waterloo Region's Light Rail Transit - plam - 01-07-2023

(01-07-2023, 05:16 PM)danbrotherston Wrote: Again, I would like to know what the point of hiring an expensive contractor to handle these things.....it's supposed to be expertise, but we don't seem to be getting that.

Plausible deniability and the lack of belief that a government can actually develop operational expertise, based on neoliberal ideology?


RE: ION - Waterloo Region's Light Rail Transit - jwilliamson - 01-08-2023

(01-07-2023, 04:58 PM)ac3r Wrote: So the trains are garbage as well as the engineering. No surprise given that they were from Bombardier and overall the project leaders tried to save every cent they could, resulting in a "rapid transit" system that shuts down in the winter, can't climb minor inclines and moves extremely slowly.

You get what you pay for.

That quote sounds like the trains are outperforming expectations. Other than the initial construction and teething issues, and how hard they are to see, what are your complaints with the vehicles?


RE: ION - Waterloo Region's Light Rail Transit - Bytor - 01-09-2023

(01-07-2023, 12:27 PM)taylortbb Wrote:
(01-06-2023, 06:20 PM)danbrotherston Wrote: These are supposed to be experts...they should know about this before hand.

There was an interesting comment on Reddit in reply to Cory, https://www.reddit.com/r/waterloo/comments/1050ifq/response_to_email_about_ion_going_offline_in_the/j38l4d5/?context=1 . I have no idea if it's true, and 50% increase in capital cost seems like an exaggeration, but I do remember that there's some sections of the route (at least King/Victoria) that are right at the maximum possible grade for the Flexity Freedom. So it seems at least somewhat plausible.

The comment in full is:
Quote:My (unofficial) understanding is that the route itself is problematic for adverse weather. Specifically, that the grade in places is steeper than the trains can be expected to climb in icing conditions. Fixing this would have required a route change which would have increased the entire ion cost by 50% or more.

The decision was made that the local economic cost of shutting it down for a day or every year or two was more palatable than increasing the project cost by that amount. Also, since they expected to be shut down in icy weather due to the grade, they didn't initially invest in other features which would allow operation in those conditions if the grade weren't an issue (ie. catenary scrapers).

Assuming this isn't exaggerated (I heard it during a casual conversation), it actually all seems pretty reasonable to me. The economic case for increasing capital expenditures by 50% in order to increase reliability from 98% to 98.25% (or whatever it would have been) is pretty weak.

However, it seems like the grade has actually been less of an issue than they originally thought, meaning that the bottleneck to operation in these conditions has been the other equipment they chose not to buy. This has the appearance of poor planning, when they actually just made a reasonable decision based on operating expectations.

There's a few problems with what SmallBig1993 said.

Quote:The decision was made that the local economic cost of shutting it down for a day or every year or two was more palatable than increasing the project cost by that amount.

But that directly contradicts the part where Goetzke says "and Keolis, the system operator, has not met its contractual requirements in the latest weather event".

Quote:Also, since they expected to be shut down in icy weather

That, too, is contradicted by what Goetzke says, because if that were the case then provisions in the contract about abut acceptable shutdowns would cover incidents like this and therefore GrandLinq would not been in violation of the contract. But given that they were deemed as not meeting contractual requirements, it says that continuing to run in relatively minor (as in not a state of emergency massive ice storm) freezing rain was expected.

Quote:Specifically, that the grade in places is steeper than the trains can be expected to climb in icing conditions. Fixing this would have required a route change which would have increased the entire ion cost by 50% or more.

Slope is a wheels on rails problem, a traction issue, not a catenary problem, which this was. None of these ice problems since 2019 have been a traction issue. They have all been problems with the catenary wires.

Combine that with plenty of places with trams a similar or worse winter conditions to us having trams have routs with gradients of 8-10% with little to no problem, and I believe our steepest gradient is 6% along King St. West the other side of the rail bridge from Central Station, leads me to think that this claim about a 50% more expensive route to be wildly exaggerated, if not completely bogus.


RE: ION - Waterloo Region's Light Rail Transit - ac3r - 01-10-2023

(01-08-2023, 01:57 AM)jwilliamson Wrote:
(01-07-2023, 04:58 PM)ac3r Wrote: So the trains are garbage as well as the engineering. No surprise given that they were from Bombardier and overall the project leaders tried to save every cent they could, resulting in a "rapid transit" system that shuts down in the winter, can't climb minor inclines and moves extremely slowly.

You get what you pay for.

That quote sounds like the trains are outperforming expectations. Other than the initial construction and teething issues, and how hard they are to see, what are your complaints with the vehicles?

That we bought trains that immediately started having welds crack. The constant wheel slippage or whatever it is when the train is just riding along like normal even on a normal day on fairly level ground, starts to shake/make noise then the driver has to slam on the brakes and speed up again. Then come first winter, we realized they couldn't make it up very minor grades.

It's clearly both an economic problem and a train/equipment problem. The region/cities were too cheap to invest in a good system (let's be honest here, this thing sucks for the most part and was approved because it was going to make developers a shit load of money with transit-oriented development plans; as a rapid transit system it blows and anyone who disagrees has no idea what they're talking about), too cheap to invest in good equipment and we went with Bombardier who have always been problematic. Let's not forget that they took 2 years longer than expected to deliver our trains, then when we finally got them they began to literally crack apart and had to be sent back.

Hundreds of millions of dollars were spent and hundreds of millions of dollars more (and, ultimately, billions more in the coming decades) so simple failures and cheaping out on basic things is unacceptable. It's no wonder so many in Cambridge don't want to spend the money on it. If getting up the grade at Courtland (near Hayward) is a challenge even without ice - on a perfectly warm summer day the train is moving, braking, moving, braking because the wheels are slipping or something - then how is it expected to navigate the Grand River Valley where the grade will be equal to dozens of meters in height?

It usually works fine, but when it doesn't, it's due to the most ridiculous reasons that should not have been allowed to be signed off on in the first place. But it all went back to spending as little as we could so we could have a bit of a renaissance in the region and make a handful of developers extremely rich, while doing nothing to improve housing or non-LRT related transit for everyone else. It was a tool for an easy mode economic boom, not a real investment in rapid transit. As such, it's pretty crap.


RE: ION - Waterloo Region's Light Rail Transit - Bytor - 01-10-2023

(01-10-2023, 01:45 PM)ac3r Wrote: The constant wheel slippage or whatever it is when the train is just riding along like normal even on a normal day on fairly level ground, starts to shake/make noise then the driver has to slam on the brakes and speed up again.

I've never experienced that, in spite of frequently riding ION.

(01-10-2023, 01:45 PM)ac3r Wrote: Then come first winter, we realized they couldn't make it up very minor grades.

And where did you hear that, specifically? All reported winter problems have been about ice on the catenary wires.

I ride ION frequently, including in the major snowstorms, and not one tram has ever had trouble on a slope. As I mentioned in another comment our steepest slop is about 6% on King St. W. just past the rail bridge from Central Station. Plenty of tram systems in similar winter climes to ours have 8% to 10% slopes and they have no problems going up hills. Not to mention that modern trams, ours included, have grit spreaders for winter weather.

(01-10-2023, 01:45 PM)ac3r Wrote: as a rapid transit system it blows and anyone who disagrees has no idea what they're talking about)

I'd say that same about you.

Except for these rare (if frustrating) incidents, ION LRT is clearing running far better than the busses it replaced, and pre-pandemic it resulted in a huge increase in transit use.

(01-10-2023, 01:45 PM)ac3r Wrote: too cheap to invest in good equipment and we went with Bombardier who have always been problematic.

No, they were not "always problematic". Thy were one of the biggest rail manufacturers on the planet before being bought by Alstom, and very popular with a good reprutation.

Serious cracks in the Bombardier façade did not appear until after the RMOW had committed to joining Metrolinx's contract.


RE: ION - Waterloo Region's Light Rail Transit - ac3r - 01-10-2023

(01-10-2023, 02:04 PM)Bytor Wrote:
(01-10-2023, 01:45 PM)ac3r Wrote: The constant wheel slippage or whatever it is when the train is just riding along like normal even on a normal day on fairly level ground, starts to shake/make noise then the driver has to slam on the brakes and speed up again.

I've never experienced that, in spite of frequently riding ION.

I'm honestly not sure what it is. You notice it more so if it's moving at a slow speed, on a grade however minor or speeding up/slowing down...but a lot of the times it is entirely random. The train will be going along like normal, then you'll notice a vibration (or something?) and the driver immediately lets off the throttle. You then hear the sand dispensers activate and then it speeds up again...until it does this again. It's definitely unrelated to actual designated points where they must lower the speed or ATC. It's frequently just random. You can be gunning it down the portion between Mill and Block line where it's entirely flat and straight, but once it gets closer to the station or the turn at Hayward, this occurs. But it's not just there, it's anywhere along the system.


RE: ION - Waterloo Region's Light Rail Transit - danbrotherston - 01-10-2023

(01-10-2023, 02:04 PM)Bytor Wrote:
(01-10-2023, 01:45 PM)ac3r Wrote: The constant wheel slippage or whatever it is when the train is just riding along like normal even on a normal day on fairly level ground, starts to shake/make noise then the driver has to slam on the brakes and speed up again.

I've never experienced that, in spite of frequently riding ION.

I have also never experienced this. I have never seen wheel slipping or stalling on the ION. I do hear the grit spreaders running (I assume this is in response to minor detected wheel slippage same as traction control in a modern car) but this is normal and the system working as it should.

The ION does experience occasional minor hunting oscillations as all trains do, but it's pretty minor, and I've never seen an operator respond to it with heavy braking.


RE: ION - Waterloo Region's Light Rail Transit - ac3r - 01-19-2023

Spotted this on Reddit:

[Image: Wn9vq5Y.png]



RE: ION - Waterloo Region's Light Rail Transit - dtkvictim - 01-19-2023

(01-19-2023, 11:15 AM)ac3r Wrote: Spotted this on Reddit:

[...]

[Image: AMfvZcr.png]


RE: ION - Waterloo Region's Light Rail Transit - bravado - 01-19-2023

If both trains hit it, would the Reddit crash counter go up by 2 or just 1?


RE: ION - Waterloo Region's Light Rail Transit - panamaniac - 01-19-2023

To be fair, they avoided the lane where turns are prohibited ....


RE: ION - Waterloo Region's Light Rail Transit - allknowing2012 - 01-20-2023

He saw the diamond on the sign and thought it was the HOV lane.