Waterloo Region Connected
Garment Street Condos | 25 & 6 fl | U/C - Printable Version

+- Waterloo Region Connected (https://www.waterlooregionconnected.com)
+-- Forum: Land Development and Real Estate (https://www.waterlooregionconnected.com/forumdisplay.php?fid=4)
+--- Forum: Urban Areas (https://www.waterlooregionconnected.com/forumdisplay.php?fid=5)
+--- Thread: Garment Street Condos | 25 & 6 fl | U/C (/showthread.php?tid=1072)

Pages: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34


RE: Garment Street Condos | 25 & 6 fl | U/C - Serendipity - 04-29-2021

Does anyone know if the last tower is still expected to be completed on time?


RE: Garment Street Condos | 25 & 6 fl | U/C - 519 - 04-30-2021

(04-29-2021, 07:08 PM)Serendipity Wrote: Does anyone know if the last tower is still expected to be completed on time?

I was told recently that occupancy for this tower is on track for January/February 2022.


RE: Garment Street Condos | 25 & 6 fl | U/C - KevinT - 05-06-2021

(04-27-2021, 01:46 PM)Spokes Wrote: I really want a Momentum project on this site.  Badly.

I really want an Ion stop in front of it to replace the other two that are way too close together.

Note: This is in regards to the old Charles St terminal site, not the Garment St condos.


RE: Garment Street Condos | 25 & 6 fl | U/C - hockeyguy99 - 05-06-2021

(04-30-2021, 01:34 PM)519 Wrote:
(04-29-2021, 07:08 PM)Serendipity Wrote: Does anyone know if the last tower is still expected to be completed on time?

I was told recently that occupancy for this tower is on track for January/February 2022.
Fall 2021


RE: Garment Street Condos | 25 & 6 fl | U/C - taylortbb - 05-07-2021

(05-06-2021, 11:04 PM)hockeyguy99 Wrote:
(04-30-2021, 01:34 PM)519 Wrote: I was told recently that occupancy for this tower is on track for January/February 2022.
Fall 2021

Momentum might be claiming that, but IMO no way that's happening. They still have several floors to pour.

Charlie West topped out months ago, and it's fall 2021 occupancy.


RE: Garment Street Condos | 25 & 6 fl | U/C - ac3r - 05-09-2021

[Image: UsSDkjl.jpg]



RE: Garment Street Condos | 25 & 6 fl | U/C - Bjays93 - 05-10-2021

Glove box looks pretty good


RE: Garment Street Condos | 25 & 6 fl | U/C - Spokes - 05-10-2021

Beautiful


RE: Garment Street Condos | 25 & 6 fl | U/C - Serendipity - 05-13-2021

(04-30-2021, 01:34 PM)519 Wrote:
(04-29-2021, 07:08 PM)Serendipity Wrote: Does anyone know if the last tower is still expected to be completed on time?

I was told recently that occupancy for this tower is on track for January/February 2022.

Really - 2022??? My occupancy date is suppose to be July 2021.  Huh


RE: Garment Street Condos | 25 & 6 fl | U/C - taylortbb - 05-13-2021

(05-13-2021, 05:53 PM)Serendipity Wrote: Really - 2022??? My occupancy date is suppose to be July 2021.  Huh

Which tower are you in? That sounds about right for upper floors of Tower 2 (originally 100 Victoria). But Tower 3 (which is the one branded Garment St) there's no way there's any occupancy until 2022.


RE: Garment Street Condos | 25 & 6 fl | U/C - foozlewoozle - 05-14-2021

(05-13-2021, 05:53 PM)Serendipity Wrote:
(04-30-2021, 01:34 PM)519 Wrote: I was told recently that occupancy for this tower is on track for January/February 2022.

Really - 2022??? My occupancy date is suppose to be July 2021.  Huh

I'm in the same boat as Serendipity for Tower 3 for July 2021. I emailed the sales rep back in March who said she expects the July date pushed back, but I haven't been given any official notice with just over two months to go.


RE: Garment Street Condos | 25 & 6 fl | U/C - taylortbb - 05-14-2021

I think a good rule of thumb is 12-14 months after your selections appointment. That's been about right for Tower 2, and is looking about right for Charlie West.


RE: Garment Street Condos | 25 & 6 fl | U/C - 519 - 05-14-2021

(05-14-2021, 12:32 AM)foozlewoozle Wrote:
(05-13-2021, 05:53 PM)Serendipity Wrote: Really - 2022??? My occupancy date is suppose to be July 2021.  Huh

I'm in the same boat as Serendipity for Tower 3 for July 2021. I emailed the sales rep back in March who said she expects the July date pushed back, but I haven't been given any official notice with just over two months to go.

My January/February timeline was per a conversation with a Momentum rep during my pre-delivery inspection appointment in late April for my unit in Tower 2.  

Also, not sure if this was mentioned before but I was told that the Condo fee for Tower 3 is about $0.48/sqft which is higher than Tower 1 & 2 ($0.42/sqft).  Difference is due to more amenities in Tower 3 (not shared with the other two).


RE: Garment Street Condos | 25 & 6 fl | U/C - tomh009 - 05-14-2021

15% higher condo fee is quite a big difference, and about $50/month for a 600 sqft unit. What additional amenities do they provide for that?


RE: Garment Street Condos | 25 & 6 fl | U/C - Walrus - 05-17-2021

(05-14-2021, 12:32 AM)foozlewoozle Wrote:
(05-13-2021, 05:53 PM)Serendipity Wrote: Really - 2022??? My occupancy date is suppose to be July 2021.  Huh

I'm in the same boat as Serendipity for Tower 3 for July 2021. I emailed the sales rep back in March who said she expects the July date pushed back, but I haven't been given any official notice with just over two months to go.

You and Serendipity need to contact a proper Momentum salesperson. The tentative occupancy of July was pushed to Nov and all purchasers were notified in March.